32
PRESSURE NODE INSTALLATION MANUAL
Environmental Monitoring Commissioning Checklist
Checklist Item Description
þ
Notes
19 Verify return and supply sensors located in respective airflow path
20 Verify CRAC/CRAH ThermaNode installation is in the supply air flow path
21 Verify sensor wiring harness does not rub against sharp edges or is able to get
pinched
22 Verify sensor wiring harness does not obstruct possible maintenance
Pressure Nodes
23 Verify hose connections correspond to low (-) and high (+)pressure areas
24 Verify hose routing:
•
(-) low-pressure hose, route to side of server or outside plenum duct
(avoiding rapid airflow)
•
(+) high pressure hose, route to sub-floor or inside plenum duct
25 Secure pressure nodes and verify for trip hazards
Validate Sensor Installation
26 Verify Server Rack ThermaNode Intake > exhaust temperatures
27 Verify CRAC/CRAH node return > supply air temperature
28 Verify Pressure node data is (+) positive
W
ebConsole
29 Verify necessary Alerts are enabled
30 Verify email server is configured (option)
31 Communicate active Alerts with site team
32 Create customer: user name and passwords
Training
33 Conduct Software and Hardware training
34 Provide Customer Support Information
Final