1.2-1
Prerequisites
1.2. Prerequisites
1.2-1 CE
symbol
If your crane is marked with a CE symbol it meets the requirements of the machine directive of the
EEA (European Economic Area).
This symbol is only valid in connection with a conformity declaration issued for your crane.
The company mounting the crane on the truck must issue a conformity declaration. If constructional
changes are made to the crane (e.g. mounting of a rope winch, remote control, raised stand or raised
seat, etc.) the CE symbol must be re-issued by the company mounting the equipment (new
conformity declaration).
If the crane bears a CE symbol, it must be fitted with an overload safety device.
Ancillary equipment must bear its own CE symbol.
In the EEA and certain other countries the crane may only be operated if it has a valid CE symbol
and valid conformity declaration.
1.2-2
Assembly, acceptance and regular inspection of the crane unit
The crane must be assembled according to the valid assembly rules of PALFINGER. The valid
Installation Instructions may be obtained from the responsible general representative. After
successful crane mounting the vehicle still has to be stable throughout the entire working area of the
crane.
In addition, country-specific assembly regulations, provisions and rules as well as provisions and
rules of the truck manufacturer are to be observed. The acceptance procedure required by law must
be carried out.
The company responsible for assembly must instruct the crane operator in the operation of the crane
and point out to the crane on handing over the crane and point out to the crane operator all possible
dangers and risks of injury.
On handover of the crane the customer is to be given the maintenance manual, operating
instructions (including assembly-related additions), and the conformity declaration for the EEA.
The firm operating the crane is responsible for ensuring that the regular inspections required by law
are carried out.
Approval from the Palfinger company is required:
If the crane is used for other operations than those intended by the PALFINGER company.
In case of structural modifications to all load-bearing components.
In case of structural modifications which affect the stability.
In case of structural modifications which obstruct the accessibility of the operating elements.
In case of structural modifications which do no longer ensure a safe crane operation.
Summary of Contents for PK 23002
Page 1: ......
Page 2: ......
Page 4: ...Inhalt ...
Page 6: ...Inhalt ...
Page 8: ...1 1 1 Overview of dangers ...
Page 16: ...1 3 6 During crane operation ...
Page 18: ...2 1 1 Checks ...
Page 20: ...2 1 1 Checks ...
Page 22: ...3 1 1 An overview of the crane ...
Page 40: ...4 1 1 During crane operation ...
Page 68: ...4 3 6 Additional equipment ...
Page 70: ...5 1 1 Ending crane operation ...
Page 80: ...5 2 1 After crane operation ...
Page 82: ...6 1 1 Maintenance ...
Page 85: ...Maintenance 6 1 3 5 8 11 12 9 4 6 5 7 16 12 4 13 1 2 3 3 W 10 18 17 11 13 15 ...
Page 94: ......