74
Sun Network QDR InfiniBand Gateway Switch Service Manual for Firmware Version 2.1 • March 2013
■
If the connector stops or binds with about 1/8 in. (2 mm) still to go, back out
and repeat
Step 8
.
9. Continue to push the connector in until you feel a detent.
10. Secure the cable into the cable management hardware.
Close hook-and-loop fasteners at bundles and securing hard points.
11. If you are installing all cables as part of a gateway replacement procedure,
repeat from
Step 6
for all cables, including the Ethernet data cables at
connectors 0A and 1A on the right side of the rear panel.
12. Replace the cover for the cable management bracket and tighten the
thumbscrews.
Related Information
■
“Install a Power Supply” on page 49
■
“Install a Fan” on page 61
■
“Replace the Battery” on page 78