19
Preparing the Site
Prepare to install the server at the installation site.
Related Information
■
“Understanding the Server” on page 1
■
“Preparing for Installation” on page 67
Site Preparation Checklist
Before installing the server, ensure that the following requirements are satisfied.
No.
Task
Link
1
Review the high-level site preparation checklist and
installation site guidelines before you begin.
“Site Preparation Checklist” on page 19
“General Installation Site Guidelines” on page 22
2
Confirm that the physical site is ready to receive the
server.
“Reviewing the Physical Specifications” on page 23
3
Ensure that the power requirements are met.
“Reviewing the Power Requirements” on page 30
4
Understand the environmental requirements and
ensure that the cooling system can maintain the
server within the ideal operating range.
“Preparing for Cooling” on page 43
5
Plan how the server will get from the loading ramp
to the installation site.
“Preparing the Unloading Route and Unpacking
Area” on page 53
6
Prepare the network server addresses and serial
connections.
Summary of Contents for sparc M5-32
Page 1: ...SPARC M5 32 and SPARC M6 32 Servers Installation Guide Part No E41215 05 December 2014 ...
Page 8: ...viii SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Page 16: ...6 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Front Components ...
Page 18: ...8 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Rear Components ...
Page 21: ...Understanding the Server 11 FIGURE DCU Locations Rear of Server ...
Page 51: ...Preparing the Site 41 ...
Page 82: ...72 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Page 106: ...96 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Page 182: ...172 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...