5.) Connect Your Oxygen Hose to the Oxygen Pressure Regulator on the Oxygen
Storage Tank -
If you are using an Oxygen Manifold as in one of the previous drawings, we
recommend another ball valve between the hose that is connected to the Oxygen
Regulator and the Oxygen Manifold. This Ball Valve can then be used as your
primary supply or shut off valve between the generator and your application.
Closing this valve nightly before turning the generator off will ensure that the
storage tank is full the next day.
As before, this Oxygen Hose and Ball Valve are not included with the generator
because the connections used from location to location can vary greatly. We can
provide these Ball Valves and Hose Assemblies, if required, but intentionally do
not include them with every machine so that we may provide you with the best
price for the basic package.
6.) Plug the Electrical Cord into an Outlet -
It is preferable that the outlet used be one that cannot be accidentally turned off.
Generators shipped within North America can be plugged into any typical 110
Volt outlet while those shipped outside North America will typically be wired to
accept a single phase 220 Volt supply.
Once connected you should be ready to begin to produce your own Oxygen.
Summary of Contents for OG-75
Page 15: ...Effective April 2006 12 Sieve Re packing Diagram...
Page 26: ...Effective April 2006 23 Process Flow Schematic...
Page 27: ...Effective April 2006 24 Process Flow Schematic Touchscreen Option...
Page 29: ...Effective April 2006 26 External Components Drawing 22 G G 22...
Page 33: ...Effective April 2006 30 Internal Components Drawing SMC SMC Direct 05 LOGIC Koyo SMC...