GATE SYSTEM INSTALLATION PROCEDURE
Printed:
10/23/2019
15-1507
OHI
OBERMEYER Hydro Inc.
30 of
36
at its base lies on the top of the comma on the bladder hinge flaps.
2.
Center the seal so that the center of the gap between the two gate
panels is parallel to the center of the interpanel seal. Do not center
the interpanel seal parallel to the gap between the hinge flaps.
3.
With the interpanel seal centered, mark the seal with a straight line
1/8” (6mm) outside the end of each hinge flap for cutting.
Interpanel Seal
Right Gate
Left Gate
Hinge Flap
Centerline of seal
should be parallel
with centerline of
space between gates
Marked cutting
point is 1/8” (6mm)
outside of the end of
the hinge flap to
create interference.
Upstream -
downstream
distance of cut is
measured in step
4
Figure 23: Description of steps 2 and 3