GATE SYSTEM INSTALLATION PROCEDURE
Printed:
10/23/2019
15-1507
OHI
OBERMEYER Hydro Inc.
8 of
36
2.
POSITIONING OF BLADDERS
1.
Use straps and a lifting mechanism to lift each bladder into position.
You will know each bladder is in the correct position because the
large holes in the bladder will fit over the anchor bolts.
2.
Fit the first 6 bladder holes from left to right over the first 6 anchors.
There is no need to fit the remaining holes over the remaining
anchors, because the bladder will be folded from right to left in the
next step.
NOTE: If bladders are identical; then there is no difference where each
bladder is placed.
Figure 1: Image of a bladder properly placed over anchor bolts