5.
Apply anti-seize to each of the hinge studs.
6.
Place hinge retainers over each set of hinge studs as shown in
drawing 121
7.
Place a flat washer over the first set of hinge studs, as shown in
section A-A of drawing 121.
8.
Thread a nut onto the first set hinge studs, as shown in section A-
A of drawing 121.
9.
Torque each nut to the anchor torque specification section below.
10.
Repeat steps 1 through 7 across the entire spillway each hinge
section at a time.
6. Main Clamp Bar, Seals, and EPDM Installation
At this stage in the gate installation, it is easiest to install the rest of the
components from left to right across the spillway
1.
Left Abutment Seal
2.
Left Abutment EPDM
3.
Gate 1 Main Clamp Bars
4.
EPDM seal 2
5.
Gate 2 Main Clamp Bars
6.
Interpanel Seal 1
7.
EPDM seal 3
8.
Gate 3 Main Clamp Bars
…..
18. Final Gate Main Clamp Bars
19. Right Abutment Seal
20. Right Abutment EPDM
The installation procedure for each of the previously listed components
can be found below
6a. Abutment Seal Installation
1.
Measure the distance from the abutment plate to the end of the hinge