Installation
3-24
Part 1024496_06
2014
Nordson Corporation
Setting Up the Melter
After physically installing the melter, it must be set up to support your
manufacturing process. Melter setup consists of enabling or making changes
to factory‐set operating parameters that affect the use and function of the
melter. The operating temperature (set‐point) of the tank and each hose and
gun is also established during melter setup.
The melter is shipped from the factory with the most commonly used
operating parameters already set up. The factory setup can be modified at
any time to suit your manufacturing process.
Quick Setup
Table 3‐4 describes the most commonly used operating parameters and their
factory settings. Review the table to determine if the factory settings for each
parameter will support your manufacturing process. If the default values for
each of these operating parameters are appropriate for your manufacturing
process, then no melter setup is required. Go directly to
Set‐point
Temperature of the Tank, Hoses, and Guns
later in this section to complete
the installation process.
If you need to make changes to the factory setup or if you want to learn about
other operating parameters, go to the next part in this section,
Operating
Parameters
.
Summary of Contents for ProBlue P10
Page 10: ...Table of Contents viii Part 1024496_06 2014 Nordson Corporation...
Page 22: ...Safety 1 12 2014 Nordson Corporation Issued 10 11...
Page 37: ...Installation 3 7 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 53: ...Installation 3 23 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 61: ...Installation 3 31 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 65: ...Installation 3 35 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 69: ...Installation 3 39 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 78: ...Installation 3 48 Part 1024496_06 2014 Nordson Corporation...
Page 108: ...Operation 4 30 Part 1024496_06 2014 Nordson Corporation...
Page 125: ...Troubleshooting 6 7 Part 1024496_06 2014 Nordson Corporation Figure 6 1 Electrical components...
Page 138: ...Troubleshooting 6 20 Part 1024496_06 2014 Nordson Corporation Figure 6 6 Removing the pump...
Page 170: ...Parts 7 6 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 177: ...Parts 7 13 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 181: ...Parts 7 17 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 212: ...Technical Data 8 8 Part 1024496_06 2014 Nordson Corporation...
Page 213: ...Technical Data 8 9 Part 1024496_06 2014 Nordson Corporation...
Page 214: ...Technical Data 8 10 Part 1024496_06 2014 Nordson Corporation...
Page 215: ...Technical Data 8 11 Part 1024496_06 2014 Nordson Corporation...
Page 216: ...Technical Data 8 12 Part 1024496_06 2014 Nordson Corporation...
Page 217: ...Technical Data 8 13 Part 1024496_06 2014 Nordson Corporation...
Page 218: ...Technical Data 8 14 Part 1024496_06 2014 Nordson Corporation...
Page 219: ...Technical Data 8 15 Part 1024496_06 2014 Nordson Corporation...
Page 220: ...Technical Data 8 16 Part 1024496_06 2014 Nordson Corporation...
Page 224: ...Calculating Melter Power Requirements A 4 Part 1024496_06 2014 Nordson Corporation...
Page 248: ...Operating Parameters B 24 Part 1024496_06 2014 Nordson Corporation...
Page 260: ...Melter Communications C 12 Part 1024496_06 2014 Nordson Corporation...
Page 315: ...400 480 Volt ProBlue Adhesive Melters E 21 Part 1024496_06 2014 Nordson Corporation...
Page 318: ...400 480 Volt ProBlue Adhesive Melters E 24 Part 1024496_06 2014 Nordson Corporation...