400/480 Volt ProBlue Adhesive Melters
E-3
Part 1024496_06
2014
Nordson Corporation
Transformer Sizing
Review the following transformer sizing procedure to ensure that your
transformer is correctly sized for the number and type of hoses/guns you
intend to use.
To size your transformer
1. Determine the total power consumption (in watts) at 230 volts for all of
your hoses and guns. Table E‐1 lists the wattages of common hoses and
guns that are sold by Nordson Corporation. If your hose or gun is not
listed in Table E‐1, refer to the identification tag that is affixed to the
hose/gun.
2. Calculate the kVA rating of the required transformer by dividing the total
wattage calculated in step 1 by 1000.
Example
From Table E‐1, an application requires two 1.8 m Auto hoses at 155
watts each and two H‐402 (T‐LP) guns at 185 watts each.
The combined wattage of the selected hoses and guns is 680 watts.
680
B
1000
=
0.68 kVA
In this example, the 1.5 kVA transformer would be adequate.
Summary of Contents for ProBlue P10
Page 10: ...Table of Contents viii Part 1024496_06 2014 Nordson Corporation...
Page 22: ...Safety 1 12 2014 Nordson Corporation Issued 10 11...
Page 37: ...Installation 3 7 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 53: ...Installation 3 23 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 61: ...Installation 3 31 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 65: ...Installation 3 35 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 69: ...Installation 3 39 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 78: ...Installation 3 48 Part 1024496_06 2014 Nordson Corporation...
Page 108: ...Operation 4 30 Part 1024496_06 2014 Nordson Corporation...
Page 125: ...Troubleshooting 6 7 Part 1024496_06 2014 Nordson Corporation Figure 6 1 Electrical components...
Page 138: ...Troubleshooting 6 20 Part 1024496_06 2014 Nordson Corporation Figure 6 6 Removing the pump...
Page 170: ...Parts 7 6 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 177: ...Parts 7 13 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 181: ...Parts 7 17 Part 1024496_06 2014 Nordson Corporation This page intentionally left blank...
Page 212: ...Technical Data 8 8 Part 1024496_06 2014 Nordson Corporation...
Page 213: ...Technical Data 8 9 Part 1024496_06 2014 Nordson Corporation...
Page 214: ...Technical Data 8 10 Part 1024496_06 2014 Nordson Corporation...
Page 215: ...Technical Data 8 11 Part 1024496_06 2014 Nordson Corporation...
Page 216: ...Technical Data 8 12 Part 1024496_06 2014 Nordson Corporation...
Page 217: ...Technical Data 8 13 Part 1024496_06 2014 Nordson Corporation...
Page 218: ...Technical Data 8 14 Part 1024496_06 2014 Nordson Corporation...
Page 219: ...Technical Data 8 15 Part 1024496_06 2014 Nordson Corporation...
Page 220: ...Technical Data 8 16 Part 1024496_06 2014 Nordson Corporation...
Page 224: ...Calculating Melter Power Requirements A 4 Part 1024496_06 2014 Nordson Corporation...
Page 248: ...Operating Parameters B 24 Part 1024496_06 2014 Nordson Corporation...
Page 260: ...Melter Communications C 12 Part 1024496_06 2014 Nordson Corporation...
Page 315: ...400 480 Volt ProBlue Adhesive Melters E 21 Part 1024496_06 2014 Nordson Corporation...
Page 318: ...400 480 Volt ProBlue Adhesive Melters E 24 Part 1024496_06 2014 Nordson Corporation...