Unit Startup
The unit is now ready to be started. The steps below outline the procedure for starting the unit and verifying proper operation of
the unit.
It is recommended that safety glasses be worn during the following procedures.
IMPORTANT NOTE: The unit is shipped with the system DISABLED in order to prevent the unit from starting when the pow-
er is first turned on. Follow the instructions below in the Preparation section to enable the compressor.
The LCD interface will show the outdoor temperature, suction pressures, discharge pressures, superheats, EEV positions,
and water in/out temperatures.
Preparation:
1. Turn the power on to the heat pump. All LED’s on the control board should turn on, the LCD interface should say “
MGT GEN2
VERx.xx
” on line 1 and “
Zeroing EEV’s
” on line 2. You should be able to hear the EEV’s moving (a clicking sound).
2.
Measure the following voltages on the power block and record them on the startup sheet: L1-L2, L2-L3, L1-L3.
3.
Connect a USB cable between the USB connector on the board and a laptop computer (if available).
4. Select the desired Control Source HYD via the PC APP Configuration Page or via the LCD display Configuration Menu.
5.
Enable the system either with the Configuration Page
System Enable/Disable
button or via the LCD display.
(IMPORTANT NOTE: compressor(s) may start on their own if Setpoint Control is selected).
Heating Mode:
1.
Activate Stage 1. The outdoor EEV(s) will begin to open and the compressor(s) will start, as will the circulator pumps.
Note that the system will start in cascade mode if the outdoor temperature is below ~50°F (meaning both refrigeration
circuits will be active), and in R134a mode only if outdoor temperature is warmer.
2.
Check the PC APP or LCD interface. The suction and discharge pressures will vary based on the outdoor temperature and the
indoor loop
temperature, and in warm weather only circuit 2 (R134a) will be active.
3.
Monitor the unit via the PC APP or LCD while the unit runs, and record the following after 10 minutes of run time:
1. R410a suction & discharge pressures (only active if in cascade mode)
2. R134a suction & discharge pressures
3. Indoor Loop In (Hot In) temperature
4. Indoor Loop Out (Hot Out) temperature
5. Indoor Delta T (should be
8-12°F / 4-6°C
)
6. Indoor flow (if available)
7. Outdoor air temperature
8. Compressor 1 & 2 L1(C) current (black wire, place meter between electrical box and compressor)
4.
Adjust the control setpoints to the desired buffer tank temperature and let the unit run through a cycle.
Record the setpoint
and R134a discharge pressure just before the unit shuts off.
Cooling Mode:
1.
Set the unit to cooling mode and adjust the cooling setpoints to activate stage 1.
Note that in cooling mode, only the R134a circuit will be active.
2.
Monitoring the unit via the PC APP or LCD display while the unit runs, record the following after 10 minutes of run time:
1. R134a suction pressure
2. R134a discharge pressure
3. Indoor Loop In temperature
4. Indoor Loop Out temperature
5. Indoor Delta T
6. Outdoor air temperature
3.
Adjust the cooling setpoints to the desired tank temperature, and allow the unit to run through a cycle. Record the
setpoint and the suction pressure when the unit shuts off.
Final Inspection:
1. Turn the power off to the unit and remove all test equipment.
2. Install the electrical box cover and the access panel on the heat pump. Install the service port caps securely to prevent
refrigerant loss.
3. Do a final check for leaks in the indoor loop piping and ensure the area is clean.
4. Turn the power on to the unit. Set the Setpoints Control (or aquastat) to the final settings and record the values.
Startup Record:
1. The installer should sign and date the Startup Record and have the startup witness or appropriate site personnel sign as well.
The startup personnel should leave the Startup Record at the site, retain a copy for filing, and send a copy to Maritime Geother-
mal Ltd. for warranty registration.
Summary of Contents for ATWC Series
Page 15: ...PRELIMINARY 24 Sep 2021 Page 15 002536MAN 00...
Page 16: ...PRELIMINARY 24 Sep 2021 Page 16 002536MAN 00...
Page 17: ...PRELIMINARY 24 Sep 2021 Page 17 002536MAN 00...
Page 18: ...PRELIMINARY 24 Sep 2021 Page 18 002536MAN 00...
Page 20: ...PRELIMINARY 24 Sep 2021 Page 20 002536MAN 00...
Page 21: ...PRELIMINARY 24 Sep 2021 Page 21 002536MAN 00...
Page 22: ...PRELIMINARY 24 Sep 2021 Page 22 002536MAN 00...
Page 23: ...PRELIMINARY 24 Sep 2021 Page 23 002536MAN 00...
Page 24: ...PRELIMINARY 24 Sep 2021 Page 24 002536MAN 00...
Page 25: ...PRELIMINARY 24 Sep 2021 Page 25 002536MAN 00...
Page 26: ...PRELIMINARY 24 Sep 2021 Page 26 002536MAN 00...
Page 27: ...PRELIMINARY 24 Sep 2021 Page 27 002536MAN 00...
Page 28: ...PRELIMINARY 24 Sep 2021 Page 28 002536MAN 00...
Page 31: ...PRELIMINARY 24 Sep 2021 Page 31 002536MAN 00...
Page 81: ...PRELIMINARY 24 Sep 2021 Page 81 002536MAN 00...
Page 82: ...PRELIMINARY 24 Sep 2021 Page 82 002536MAN 00...
Page 83: ...PRELIMINARY 24 Sep 2021 Page 83 002536MAN 00...
Page 84: ...PRELIMINARY 24 Sep 2021 Page 84 002536MAN 00...
Page 85: ...PRELIMINARY 24 Sep 2021 Page 85 002536MAN 00...
Page 86: ...PRELIMINARY 24 Sep 2021 Page 86 002536MAN 00...
Page 87: ...PRELIMINARY 24 Sep 2021 Page 87 002536MAN 00...
Page 88: ...PRELIMINARY 24 Sep 2021 Page 88 002536MAN 00...
Page 89: ...PRELIMINARY 24 Sep 2021 Page 89 002536MAN 00...
Page 90: ...PRELIMINARY 24 Sep 2021 Page 90 002536MAN 00...
Page 91: ...PRELIMINARY 24 Sep 2021 Page 91 002536MAN 00...
Page 92: ...PRELIMINARY 24 Sep 2021 Page 92 002536MAN 00 Dimensions ATWC 45 55...
Page 93: ...PRELIMINARY 24 Sep 2021 Page 93 002536MAN 00 Dimensions ATWC 45 55...
Page 94: ...PRELIMINARY 24 Sep 2021 Page 94 002536MAN 00 Dimensions ATWC 65...
Page 95: ...PRELIMINARY 24 Sep 2021 Page 95 002536MAN 00 Dimensions ATWC 65...
Page 96: ...PRELIMINARY 24 Sep 2021 Page 96 002536MAN 00 Dimensions ATWC 75 80 100...
Page 97: ...PRELIMINARY 24 Sep 2021 Page 97 002536MAN 00 Dimensions ATWC 75 80 100...