PRELIMINARY: 24-Sep-2021
Page 55
002536MAN-00
The ATWC-Series Startup Record located in this manual is used in conjunction with this startup procedure to provide a detailed
record of the installation. A completed copy should be left on site, a copy kept on file by the installer, and a copy should be sent to
Maritime Geothermal Ltd.
Check the boxes or fill in the data as each step is completed. For data boxes, circle the appropriate units. Fill in the top section
of all three copies, or one copy if photocopies can be made after the startup has been completed.
Pre-Start Inspection
Outdoor Unit:
1.
Ensure both circuits have been pressure tested, vacuumed to 500 microns and any extra charge required has been added.
2.
Ensure all 4 access valves have been fully opened and the caps have put been back on and tightened. Check the caps for
leaks.
3.
Ensure the outdoor unit is securely mounted in place.
4.
Ensure the power and controls signals to the outdoor unit are properly connected, neat, and securely fastened.
5. Ensure fan outlet is clear of obstructions.
Indoor Loop (Hydronic Loop):
1.
Verify that all shutoff valves are fully open and there are no restrictions in the piping from the heat pump to the indoor loop,
and that full flow is available to the heat pump.
2.
Verify that the entire system has been flooded and all the air has been purged as much as possible.
Further purging may
be required after the system has been operating for a while.
3.
Verify that the loop contains the proper mix of antifreeze (if used) for the intended application. If applicable, record the type
of antifreeze and the mixture value on the startup sheet; circle % vol. or % weight.
4.
Record the static loop pressure on the startup sheet.
Electrical:
1. Ensure the power to the unit is off.
2.
Verify all high voltage connections. Ensure that there are no stray wire strands, all connections are tight, and the ground
wire is connected tightly to the ground connector.
3.
Record the circuit breaker size and wire gauge for the heat pump.
4.
Verify that the control connections to the unit are properly connected and all control signals are off, so that the unit will not start
up when the power is turned on.
5.
Verify that the circulator pumps are connected to the proper voltage terminals in the heat pump. Record the voltages of the
circulator pumps.
6.
Ensure all access panels except the one that provides access to the electrical box are in place.
Startup Procedure
Summary of Contents for ATWC Series
Page 15: ...PRELIMINARY 24 Sep 2021 Page 15 002536MAN 00...
Page 16: ...PRELIMINARY 24 Sep 2021 Page 16 002536MAN 00...
Page 17: ...PRELIMINARY 24 Sep 2021 Page 17 002536MAN 00...
Page 18: ...PRELIMINARY 24 Sep 2021 Page 18 002536MAN 00...
Page 20: ...PRELIMINARY 24 Sep 2021 Page 20 002536MAN 00...
Page 21: ...PRELIMINARY 24 Sep 2021 Page 21 002536MAN 00...
Page 22: ...PRELIMINARY 24 Sep 2021 Page 22 002536MAN 00...
Page 23: ...PRELIMINARY 24 Sep 2021 Page 23 002536MAN 00...
Page 24: ...PRELIMINARY 24 Sep 2021 Page 24 002536MAN 00...
Page 25: ...PRELIMINARY 24 Sep 2021 Page 25 002536MAN 00...
Page 26: ...PRELIMINARY 24 Sep 2021 Page 26 002536MAN 00...
Page 27: ...PRELIMINARY 24 Sep 2021 Page 27 002536MAN 00...
Page 28: ...PRELIMINARY 24 Sep 2021 Page 28 002536MAN 00...
Page 31: ...PRELIMINARY 24 Sep 2021 Page 31 002536MAN 00...
Page 81: ...PRELIMINARY 24 Sep 2021 Page 81 002536MAN 00...
Page 82: ...PRELIMINARY 24 Sep 2021 Page 82 002536MAN 00...
Page 83: ...PRELIMINARY 24 Sep 2021 Page 83 002536MAN 00...
Page 84: ...PRELIMINARY 24 Sep 2021 Page 84 002536MAN 00...
Page 85: ...PRELIMINARY 24 Sep 2021 Page 85 002536MAN 00...
Page 86: ...PRELIMINARY 24 Sep 2021 Page 86 002536MAN 00...
Page 87: ...PRELIMINARY 24 Sep 2021 Page 87 002536MAN 00...
Page 88: ...PRELIMINARY 24 Sep 2021 Page 88 002536MAN 00...
Page 89: ...PRELIMINARY 24 Sep 2021 Page 89 002536MAN 00...
Page 90: ...PRELIMINARY 24 Sep 2021 Page 90 002536MAN 00...
Page 91: ...PRELIMINARY 24 Sep 2021 Page 91 002536MAN 00...
Page 92: ...PRELIMINARY 24 Sep 2021 Page 92 002536MAN 00 Dimensions ATWC 45 55...
Page 93: ...PRELIMINARY 24 Sep 2021 Page 93 002536MAN 00 Dimensions ATWC 45 55...
Page 94: ...PRELIMINARY 24 Sep 2021 Page 94 002536MAN 00 Dimensions ATWC 65...
Page 95: ...PRELIMINARY 24 Sep 2021 Page 95 002536MAN 00 Dimensions ATWC 65...
Page 96: ...PRELIMINARY 24 Sep 2021 Page 96 002536MAN 00 Dimensions ATWC 75 80 100...
Page 97: ...PRELIMINARY 24 Sep 2021 Page 97 002536MAN 00 Dimensions ATWC 75 80 100...