Drainage pipe installation
Installation
97
6.3 Drainage test
6.3.1 Water leakage test
After finishing the construction of drainage pipe system, fill the pipe with water and keep it for 24 hours to
check whether there is leakage at joint section.
6.3.2 Water discharge test
1. Natural drainage mode(the indoor unit with outdoor drainage pump)
Infuse above 600ml water through water test hole slowly into the water collector, observe whether the
water can discharge through the transparent hard pipe at drainage outlet.
2. Pump drainage mode
2.1 Disconnect the plug of water level switch, remove the cover of water test hole and slowly infuse about
2000ml water through the water test hole, be sure that the water will not touch the motor of drainage
pump.
2.2 Power on and let the air conditioner operate for cooling. Check operation status of drainage pump, and
then connect the plug of water level switch, check the operation sound of water pump and observe
whether the water can discharge through the transparent hard pipe at drainage outlet. (In light of the
length of drainage pipe, water shall be discharged about 1 minute delayed)
2.3 Stop the operation of air conditioner, power off the power supply and put the cover of water test hole
back to the original place.
a. After stopped the air conditioner 3 minutes, check whether there is anything abnormal. If drainage pipes
have not been distributed properly, over back-flow water shall cause the flashing of alarm indicator at
remote-controlled receiving board and even water shall run over the water collector.
b. Continuously infusing water until water level alarmed, check whether the drainage pump could
discharge water at once. If water level does not decline under warning water level 3 minutes later, it
shall cause shutdown of unit. When this situation happens, the normal startup only can be recovered by
turning down power supply and eliminating accumulated water.
Note:
Drain plug at the main water-containing plate is used for eliminating accumulated water in
water-containing plate when maintaining air conditioner fault. During normal operation, the plug shall be
filled in to prevent leakage.
6.4 Insulation work of drainage pipe
Refer the introduction to the insulation engineering parts.
Summary of Contents for MUCR-H6 Series
Page 15: ...Air Velocity Distributions Reference Data Indoor Units 13 30 42K Cooling Heating ...
Page 16: ...Air Velocity Distributions Reference Data 14 Indoor Units 48 60K Cooling Heating ...
Page 21: ...Field Wiring Indoor Units 19 10 Field Wiring ...
Page 30: ...Static Pressure 28 Indoor Units 5 Static Pressure MUCR 12 H6 MUCR 18 H6 ...
Page 31: ...Static Pressure Indoor Units 29 MUCR 24 H6 MUCR 30 H6 ...
Page 32: ...Static Pressure 30 Indoor Units MUCR 36 H6 MUCR 42 H6 MUCR 48 H6 MUCR 48 H6T MUCR 60 H6T ...
Page 41: ...Service Space Indoor Units 39 3 Service Space ...
Page 52: ...50 Indoor Units 10 Field Wiring ...
Page 61: ...Field Wiring Indoor Units 59 10 Field Wiring MUCSR 12 H6 MUCSR 18 H6 ...
Page 64: ...Dimensions 62 Outdoor Units Model Unit mm W D H W1 A B 48 60 952 415 1333 1045 634 404 ...
Page 95: ...Refrigerant pipe installation Installation 93 ...