MK-370
Revision 06/05, Effective Date June 17, 2005
Page 16
SETUP, ADJUSTMENT and OPERATION
SETUP:
1. Pre-start Inspection:
Prior to beginning work, a pre-start inspection of the saw should be preformed.
2. Water Pump Preparation:
1.
To prevent the possibility electrical shock, the MK-370 MUST be de-energized when preparing
the Water Pump for operation.
2.
To prevent the possibility of electrical shock, use only MK Diamond qualified replacement parts
(A)
Install Water Pump Discharge
Fitting
(B)
Press the end of the Cooling
Transfer Tube onto the Water
Pump Discharge Fitting
Off
Position
Inspect for
damage
Inspect for
cracks or cuts
Inspect for cracks,
de-bonding, etc.
(A)
Ensure the ON/OFF Switch is
in the OFF position
(B)
Inspect the Pump Assembly for
damage – ensure the cord is
free of cracks or cuts
(C)
Inspect the Diamond Blade for
damage – verify the blade is
correct for the material being cut
(D)
Inspect the MK-370 for
damage – ensure the cord is
free of cracks or cuts
Inspect for
damage
ON/OFF
Switch
Discharge
Fitting
Pump
(C)
Connect the Cooling Transfer
Tube to the inlet connection of
the Blade Guard
Discharge
Fitting
Cooling
Transfer Tube
Press on
Cooling
Transfer
Tube
Inlet
connection
Press on
(B)
Verify the Movable Cutting
Table moves freely
Verify ease of movement
(See Maintenance section
if problems exist)