Maintenance and Testing Schedule
Maintenance
10 - 4
BP10 Operator’s Manual
10.5
Maintenance and Testing Schedule
The following maintenance and tests, except for visual inspection, power on test, and
battery check, shall be carried out by the service personnel only. Contact your service
personnel if any maintenance is required. Make sure to clean and disinfect the
equipment before any test and maintenance.
10.6
Power-On Test
Verify that the startup logo screen displays and a beep sounds after power on the device.
10.7
Checking the Device Information
To view the information about the device copyright information, serial number, system
software, hardware and MPAN version, you can select
System Info
in the main menu.
10.8
NIBP Leakage and Pressure Tests
The NIBP leakage and pressure tests checks the integrity of the system and of the valve.
Contact your service personnel to perform NIBP leakage and pressure test.
10.9
Electrical Safety Test
The electrical safety test aims to detect abnormalities that, if undetected, could prove
dangerous to either the patient or the operator. Contact your service personnel to
perform the electrical safety test.
Check/Maintenance Item
Recommended Frequency
Visual inspection
When first installed or reinstalled.
NIBP test
Pressure check
1.
If the user suspects that the measurement is
incorrect.
2.
Following any repairs or replacement of rele-
vant module.
3.
Once a year.
Leakage test
Power-on test
1.
When first installed or reinstalled.
2.
Following any maintenance or the replace-
ment of any main unit parts.
Electrical safety test
At least once every two years or as needed.
Battery check
Functionality test
1.
When first installed.
2.
Whenever the battery is replaced.
Performance test
When the battery run time reduced significantly.
Summary of Contents for BP10 NIBP Module
Page 1: ...BP10 NIBP Module Operator s Manual...
Page 2: ......
Page 11: ...BP10 Operator s Manual 1 1 1 Safety Safety Information 1 2 Equipment Symbols 1 5...
Page 16: ...Equipment Symbols Safety 1 6 BP10 Operator s Manual This page intentionally left blank...
Page 38: ...Service Menu Configuring BP10 4 6 BP10 Operator s Manual This page intentionally left blank...
Page 73: ...BP10 Operator s Manual 11 1 11 Accessories NIBP Accessories 11 2 Miscellaneous 11 3...
Page 76: ...Miscellaneous Accessories 11 4 BP10 Operator s Manual This page intentionally left blank...
Page 87: ...BP10 Operator s Manual B 1 B EMC...
Page 93: ...BP10 Operator s Manual C 1 C FCC Compliance...
Page 95: ...BP10 Operator s Manual D 1 D Symbols and Abbreviations Units D 2 Symbols D 3 Abbreviations D 3...
Page 98: ...Abbreviations Symbols and Abbreviations D 4 BP10 Operator s Manual P power PR pulse rate...
Page 99: ......
Page 100: ...P N 046 011008 00 4 0...