Maintenance Manual
MAN-00
135
GENIO DC
(BS-III & BS-IV)
JULY 2011
/Rev1
The repair methods given by the manufacturer in this document are based on the technical specifications
,
current at the time of release. The methods may be modified as a result of changes
introduced by the manufacturer in the production of the various component units and accessories from which the vehicles are manufactured. The reproduction, translation, transmission, in part of
or
whole of the present document, are prohibited without the prior written consent of Mahindra & Mahindra Ltd. The use of this document by any person other than the trained personnel, at the
Authorized Service Centre of Mahindra & Mahindra Ltd., will amount to unauthorized use and shall be liable for penalty/prosecution
© 2011 Mahindra & Mahindra Ltd.
23
•
‘LH’
rough thread is etched on the lock nut which is only to be fitted on RH side. There is no
any mark on lock nut which is to be fitted on LH side axle shaft.
Left Hand Rough Thread – ‘LH’ marking
Right Hand Rough Thread – No any mark
Match the washer lug to the lock nut groves. At
least one lug to be locked.
Use small drift/ flat screw driver and hammer to
press and lock the lugs.
Apply
Locktite 5060
on wheel end shim interface.
•
Assemble the drum brake assembly
components.
•
Connect the brake bundy tube to the wheel
cylinder and locate parking brake cable.
•
Fit the Brake drum and tighten the drum
locking screw.
Post fitment activities –
•
Assemble wheel and remove the jacks.
•
Top up brake fluid and do the brake bleeding. Ensure and use correct fluid only.
•
Check and do the parking brake lever adjustment, if require.
•
Check the differential oil level, top up if required. Ensure and use recommended fluid only.
•
Assemble wheel and remove the jacks.
•
Brake system bleeding to be as per recommended.
Wheel bearings to be lubricate at every 50000kms.
If the activity is done on a 2 post lift, ensure that the LSPV spring is
disconnected before lifting the vehicle & re-connect the LSPV spring & ensure that
the setting height is correct after job complete.