4
48-635 E3 Modulevel
®
Displacer Level Transmitter
1.0
QuickStart Installation
1.1
Getting Started
1.1.1 Equipment and Tools
No special equipment or tools are required to install E3
Modulevel
®
. The following items are recommended:
• Wrenches, flange gaskets and flange bolting appropriate for
process connection(s)
• Flat-blade screwdriver
• Level
•
1
⁄
8
" Allen wrench
• Power supply
• Digital multimeter
• 250 to 450 ohm resistor for HART communication
1.1.2 Configuration Information
Some key information is needed to configure the
E3 MODULEVEL transmitter. Complete the following
operating parameters table before beginning configuration.
1.2
QuickStart Mounting
NOTE: Confirm the style and process connection size/type of the
E3 MODULEVEL transmitter. Ensure it matches the require-
ments of the installation before continuing with the QuickStart
installation.
1.2.1 Tank Top
1. If applicable, adjust and trim the adjustable hanger cable
assembly to the required length and mount it between the
stem and displacer.
Display
Question
Answer
LvlUnits
What units of measurement will be used?
Lvl Ofst
What is the desired level reading when the
level is at the calibrated zero reference
(typically bottom of the displacer)?
Proc SG
What is the actual SG of the process liquid at
operating temperature?
OperTemp
What is the actual operating temperature?
Set 4mA
What should the level reading be at the 4 mA
set point?
Set 20mA
What should the level reading be at the 20
mA set point?