8. Connect refrigerant lines. Reference procedure later in this chapter.
9. Install all ends, caps, and trim per the applicable instructions contained in the Assembly
chapter of this manual.
10. Remove shipping tape on fluorescent lamps and remove all other shipping material.
11. Refer to the operational start up procedures later in this manual. If multiple cases are to be
installed, refer to the following paragraph for installing subsequent cases.
Installing Subsequent Cases
If additional cases are to be installed, follow the same procedures as described in the installing
first case procedure (above), except the following:
1. Ensure all case expansion valves are correct.
2. Do not install electrical, drain lines, or refrigerant lines until all the cases have been
set/placed into position.
3. Do not install case trim, ends, or caps until all cases have been set into position and
properly joined.
4. Before lining up cases using the front and rear edges as a baseline, inspect refrigeration
lines, electrical connections and controls to insure cases are in proper line up and are in
proper sequence.
5. Move cases as near their permanent location as possible before removing shipping braces,
skids or rollers. Note: All cases are factory numbered with line up and position numbers.
Make sure that cases are installed in order. (line up sticker found on the front of each case).
6. Remove skids and shipping braces. Install approximately a 5/16" bead of sealer at one end
of case as noted by a phantom line on cross-section.
7. Move cases as close together as possible and level by using the shims provided. Refer to
the leveling cases procedure located in the Adjustments chapter of this manual for the
proper shimming procedure.
CASES MUST BE LEVELED FROM FRONT TO BACK
END-TO-END AND SUPPORTED CONTINUOUSLY AS NEEDED WITH SHIMS
.
8. Install plexiglass divider, as required.
9. Remove shipping tape on fluorescent lamps and remove all other shipping material.
10. Refer to the operational start up procedures later in this manual.
UNIT INSTALLATION
22
Summary of Contents for 6RLG3
Page 3: ...2 6 2006 2 Addendum Ballast Relocation 2 ...
Page 5: ...2 6 2006 4 Addendum Ballast Relocation Wiring Diagram Both Canopy and Raceway 4 ...
Page 6: ...2 6 2006 5 Addendum Ballast Relocation Wiring Diagram for Canopy Light 5 ...
Page 9: ...Plan Views and Cross Sections D6L D6 D6H 8 ...
Page 10: ...D6RL D6R 9 ...
Page 11: ...QD6 10 ...
Page 34: ...D6 Electrical Model Table QD6 1 3 04 Through D6H 1 3 6 UNIT INSTALLATION 33 ...
Page 35: ...D6 Electrical Model Table D6H 1 3 6 Through D6R 1 3 4 UNIT INSTALLATION 34 ...
Page 36: ...D6 Electrical Model Table D6R 1 3 4 Through D6RL G 1 6 UNIT INSTALLATION 35 ...
Page 39: ...Wiring Diagram UNIT INSTALLATION 38 ...
Page 40: ...Wiring Diagram Canopy One 1 and Two 2 Light Rows UNIT INSTALLATION 39 ...
Page 41: ...Wiring Diagram Canopy Two 2 and Three 3 Light Rows UNIT INSTALLATION 40 ...
Page 42: ...Wiring Diagram Canopy Two 2 Light Rows and Nose Light UNIT INSTALLATION 41 ...
Page 43: ...Wiring Diagram Off Cycle Defrost UNIT INSTALLATION 42 ...