KONRAD 600B SERIES INSTALLATION GUIDE
JANUARY 2019 - V4.0
PAGE 65
Step 12: U-Joint Extension Shaft Installation
12.1 Verify correct shaft length and installation parameters
as defined in the Alignment Specifications Chart (on
previous page) and the alignment procedure from Step 11
in this manual before proceeding.
12.2 If applicable, bolt transmission output flange adapter on
to the transmission output flange. Apply
Loctite
to the
fasteners before tightening. Torque fasteners correctly
according to their size.
12.3 Bolt u-joint shaft onto gimbal carrier flange. Apply
Loctite
to the four (4) fasteners before tightening. Torque to 89 lb.
ft. (121 Nm).
NOTE:
Ensure pilot is correctly sized and fully engaged
(if applicable).