Service Manual
6-32
7F3318 2005 July Rev. B
6-4-8.
DC Power Supply
The DC Power Supply receives 120 volts ac from the secondary of Power Transformer T1 when Circuit
Breaker CB1 and the Power Switch are closed. The power supply provides the following outputs to the
MCS Board, which distributes dc power to the remainder of the MCS.
•
+24 volts + 5 %
•
+12 volts + 5 %
•
-12 volts + 5 %
•
+5 volts (VCC) + 5 %
The Service Switch and interlocks on the front door, rear panel, and top hood can int12 volt and/or
+24 volt dc power to certain circuits, as shown on sheet 2 of the functional diagrams in Section 10.
6-4-9.
MCS Print Sequence of Operation
The MCS is involved in six basic operations in the normal course of printing a sheet of film. These,
described in Figure 6-16, are the following:
•
Power up and self-test. (For details of the process, see Figures 7-1 through 7-7 in the
Troubleshooting section of this manual.)
•
Pick up film. (See Figure 6-17.)
•
Load the exposure platen (See Figure 6-18.)
•
Expose the film (See Figure 6-19.)
•
Unload the platen (See Figure 6-20.)
•
Process the film (See Figure 6-21.)
In addition to the basic printing operations, the folloiwng operations are flowcharted:
•
Front door close (See Figure 6-22.)
•
Front door open (See Figure 6-23.)
•
RF Tag Sequence at Cartridge Opening (See Figure 6-24.)
•
RF Tag Write and Calibration Count (See Figure 6-25.)
Note
Dotted lines between components on the flowcharts indicate that the function is a MicroComm
subsystem operation.
Summary of Contents for DryView 8150
Page 1: ...SERVICE MANUAL Kodak DryView 8150 LASER IMAGER 1961259 7F3318 07 05 ...
Page 20: ...Service Manual 1 6 7F3318 2005 July Rev B BLANK PAGE ...
Page 34: ...Service Manual 2 14 7F3318 2005 July Rev B 6 Remove the 2 SCREWS and 2 TAGS 6 ...
Page 50: ...Service Manual 2 30 7F3318 2005 July Rev B 6 Check each parameter ...
Page 91: ...Section 2 Installation 2 71 2005 July Rev B 7F3318 BLANK PAGE ...
Page 105: ...Service Manual 3 14 7F3318 2005 July Rev B BLANK PAGE ...
Page 182: ...Section 4 Disassembly Reassembly 4 77 2005 July Rev B 7F3318 BLANK PAGE ...
Page 196: ...Service Manual 5 14 7F3318 2005 July Rev B Figure 5 9 Cleaning the HEAT SHIELD and ROLLERS ...
Page 200: ...Service Manual 5 18 7F3318 2005 July Rev B Figure 5 11 Adjusting the DIVERTER ...
Page 236: ...Service Manual 6 34 7F3318 2005 July Rev B Figure 6 17 Pickup Operation Sheet 1 of 3 ...
Page 238: ...Service Manual 6 36 7F3318 2005 July Rev B Figure 6 17 Pickup Operation Sheet 3 of 3 ...
Page 240: ...Service Manual 6 38 7F3318 2005 July Rev B Figure 6 18 Load Platen Operation Sheet 2 of 2 ...
Page 241: ...Section 6 Theory of Operation 6 39 2005 July Rev B 7F3318 Figure 6 19 Expose Operation ...
Page 242: ...Service Manual 6 40 7F3318 2005 July Rev B Figure 6 20 Unload Platen Operation ...
Page 244: ...Service Manual 6 42 7F3318 2005 July Rev B Figure 6 21 Processor Operation Sheet 2 of 2 ...
Page 246: ...Service Manual 6 44 7F3318 2005 July Rev B Figure 6 22 Front Door Open Operation Sheet 2 of 2 ...
Page 252: ...Service Manual 6 50 7F3318 2005 July Rev B Figure 6 27 Sequence of AIQC and GSM Functions ...
Page 444: ...Service Manual 8 102 7F3318 2005 July Rev B BLANK PAGE ...
Page 466: ...Service Manual 9 22 7F3318 2005 July Rev B BLANK PAGE ...
Page 468: ...Service Manual 10 2 7F3318 2005 July Rev B BLANK PAGE ...
Page 469: ......