3. Putting in Operation
3.1 First Use
The controller comes preset to default values as shown in Table 4.1.
On powerup, display test runs first. The display momentarily shows
•
type of controller (e.g.
N214
N214
N214
N214
)
•
firmware version (e.g.
1
11
1
.
2
22
2
)
•
type of measurement voltage set (
U=LN
U=LN
U=LN
U=LN
or
U=LL
U=LL
U=LL
U=LL
)
•
metering current transformer secondary side nominal value set (
I=5A
I=5A
I=5A
I=5A
or
I=1A
I=1A
I=1A
I=1A
)
If the measurement voltage connection is correct, the automatic connection configuration detection
process starts.
If no measurement voltage is detected,
U=0
U=0
U=0
U=0
will flash on the display
.
3.2 Automatic Connection Configuration Detection Process
The controller’s default measurement voltage and current connection parameters are set as follows:
•
type of measurement voltage set to phase voltage (“LN”, parameter 15)
•
method of connection of U and I not defined (parameter 16)
•
compensation system nominal voltage
U
NOM
set to 230 V (parameter 18)
If the method of connection is not defined, the controller cannot evaluate instantaneous power factor
and this condition is indicated by both trend LEDs flashing simultaneously. In such an event, the
controller carries out automatic connection configuration detection process.
For the controller to be able to carry out this automatic connection configuration detection process, the
following conditions must be met:
•
controller operation is not disabled (i.e. the
Manual
LED is dark)
•
controller is in the control mode, i.e. the numeric display mode is
Measurement
•
measurement voltage of the minimum value required is connected
If meeting the three above conditions, the controller starts the automatic connection configuration
detection process.
The process may have up to seven steps. The controller makes four measuring attempts in each step
in which it consecutively connects and disconnects sections 1 through 4. It, at the same time,
assumes that power factor capacitors are connected to at least two of the sections (if any choke
connected to sections 1 through 4, detection process fails). The two following messages are shown,
one after another, in each measurement attempt on the numerical display:
Summary of Contents for NOVAR-1 Series
Page 66: ...Novar 1xxx KMB systems 66 Novar1106 installation...
Page 67: ...Novar 1xxx KMB systems 67 Novar1114 installation...
Page 68: ...Novar 1xxx KMB systems 68 Novar1206 installation low voltage measurement...
Page 69: ...Novar 1xxx KMB systems 69 Novar1214 installation high voltage measurement...
Page 70: ...Novar 1xxx KMB systems 70 Novar1114 S400 installation...
Page 73: ...Novar 1xxx KMB systems 73 Novar1414 installation low voltage measurement...