7.1
Checks before initial start-up
Carry out the following activities before taking the Modul E-Drive
landing gear into operation:
Check the attachment and correct tightening torque of the
bolts for the landing gear.
Check that the crank has been installed correctly and is func-
tioning (freewheel).
Check that the crank of the landing gear is not connected
and that it is in the parked position, so that it will not be spun
around when the electric landing gear drive is running.
Check the attachment of the electrical cables.
Check that the electrical cables are routed without kinks and
so that they cannot chafe.
Check that the electrical cables are an adequate distance
away from hot components.
Check that the supply line has been connected correctly.
Check that there is adequate fusing for the 24 V electrical
power supply on the semi-trailer tractor side (at least 15 A).
ADVICE!
All semi-trailer tractors that are intended for use with
the semi-trailer fitted with the Modul E-Drive must pro-
vide adequate fusing at the selected voltage pick-off
point.