6
Installation
ADVICE!
Take the following into account when installing the elec-
trical cables:
The electrical cables must not be secured to brake
cables.
The electrical cables must be routed at an ade-
quate distance from heat sources and moving parts
of the semi-trailer. If necessary the cables must be
fitted with a heat protection corrugated tube or a
chafing guard.
The electrical cables must be routed so that they
have no kinks and cannot chafe.
The electrical cables are to be secured using cable
ties (for example to the semi-trailer’s wiring har-
ness).
Please note the following before carrying out any work
to the electrical system:
Disconnect the semi-trailer from the electrical
power supply of the semi-trailer tractor.
Disconnect the negative terminal of the vehicle
battery (if there is one on the semi-trailer).
When working on the semi-trailer tractor, read out
the error memory of the semi-trailer tractor before
disconnecting the negative terminal from the vehi-
cle battery.
Installation of the E-Drive landing gear module with previous
removal of existing landing gears
Raise the landing gear using the crank (remove the load).
Remove the left and right landing gear.
Install the Modul E-Drive landing gear and tighten it to the
prescribed tightening torque. Make sure that the landing
gears are extended or retracted by the same amount.
When mounting the right landing gear, bolt on the standard
console with the landing gear according to the available space
(left/right). Note that the bolts for this are 20 mm longer than
when installing without standard console. Alternatively, the
control elements can be mounted in the supplied universal
bracket and positioned at any point (note the cable length).
Installation of the E-Drive landing gear module without previous
removal of existing landing gears (first-time installation)
In addition, please note the following:
Secure the landing gear strut at an angle of min. 45°, as
shown in Fig E-Drive/006.
The connection shaft must be 25 mm shorter than the dis-
tance between the fastening flanges on the trailer vehicle.
EN
Modul E-Drive
MUB 006 001 M01
(REV-D)
07-2020
19