46
OM131
Chapter 3
P1939-OM-131 R11
3.4 P
OST
-
DIVE
PROCEDURES
3.4.1
Post-dive check list (Normal operations)
1.
Check the SLS System contents gauge. Recharge the cylinders if any loss of gas is indicated.
Check also against Table 1.1, page 12 or Table 3.2 or SLS System duration at working
depths to ascertain if charging is required.
N
OTE
The backpack must be removed from the dive complex in order to recharge the cylinders.
2.
Remove the outer side door.
3.
Remove the inner door and extract the CO
2
scrubber canister (section 3.1.2). Check for the
presence of moisture.
4.
Replace the CO
2
scrubber canister if the sodalime is damp or if the SLS System has been
actuated and used. The scrubber canister must be replaced or refilled after 24 hours in the
SLS System (section 3.1.3).
5.
Replace the CO
2
scrubber canister into the backpack (section 3.1.2).
6.
Replace and secure the outer door.
7.
Check the packaging of the counterlungs and wash the actuation cable assembly,
counterlung enclosures and cable sleeves with fresh water as necessary.
8.
Stow the SLS System ready for the next dive.
3.4.2
Post-dive check list (After SLS system activation)
1.
Remove the SLS System backpack from the dive complex.
2.
If necessary, fully discharge the gas cylinders (section 3.4.3).
3.
Remove the outer side door.
4.
Remove the CO
2
scrubber door and extract the CO
2
scrubber canister (section 3.1.2). Check
inside for water.
5.
Remove the CO
2
scrubber lift mechanism by pressing down on the centre and sliding it
towards the door opening to release it from the locating feature in the penetrators.
6.
Remove the sponge pad (Fig 3.7, Item 5) and rinse with freshwater. Squeeze out any surplus
water before installation. If the sponge material is too dry, it is very slow to absorb water.
7.
Remove the thermal regenerator (Fig 3.7, Item 1) by releasing the wing nut.
8.
Clean the gas space above the thermal regenerator.
9.
Remove the counterlungs and the counterlung hoses from the backpack. Wash everything in
warm, soapy water, then rinse and allow to dry.
10.
Re-install the thermal regenerator (Fig 3.7, Item 1) and secure it in place with the wing nut.
Summary of Contents for Divex SLS Mk IV
Page 2: ...Intentionally Blank...
Page 4: ...ii OM131 Approval Sheet P1939 OM 131 R11 Intentionally Blank...
Page 6: ...iv OM131 Preface P1939 OM 131 R11 Intentionally Blank...
Page 8: ...vi OM131 List of Abbreviations P1939 OM 131 R11 Intentionally Blank...
Page 10: ...viii OM131 Warnings P1939 OM 131 R11 Intentionally Blank...
Page 12: ...x OM131 Table of Contents P1939 OM 131 R11 Intentionally Blank...
Page 15: ...OM131 3 P1939 OM 131 R11 Chapter 1 Fig 1 1 SLS System Mk IV...
Page 16: ...4 OM131 Chapter 1 P1939 OM 131 R11 Fig 1 2 SLS system layout...
Page 32: ...20 OM131 Chapter 2 P1939 OM 131 R11 Fig 2 4 Two stage regulator Fig 2 5 Spool valve...
Page 42: ...30 OM131 Chapter 2 P1939 OM 131 R11 Intentionally Blank...
Page 53: ...OM131 41 P1939 OM 131 R11 Chapter 3 Fig 3 3 Hose Lanyards...
Page 54: ...42 OM131 Chapter 3 P1939 OM 131 R11 Fig 3 4 SLS System Mk IV Rear View...
Page 55: ...OM131 43 P1939 OM 131 R11 Chapter 3 Fig 3 5 SLS System Mk IV Front View...
Page 64: ...52 OM131 Chapter 3 P1939 OM 131 R11 Intentionally Blank...
Page 82: ...70 OM131 Chapter 4 P1939 OM 131 R11 Fig 4 7 Annual Maintenance Two Stage Regulator...
Page 86: ...74 OM131 Chapter 4 P1939 OM 131 R11 Fig 4 8 Annual Maintenance Single Stage Regulator...
Page 109: ...OM131 97 P1939 OM 131 R11 Chapter 5 Fig 5 2 Backpack Assembly Drawing P1939229S1...
Page 111: ...OM131 99 P1939 OM 131 R11 Chapter 5 Fig 5 4 Scrubber Housing Assembly Drawing P1939131S1...
Page 118: ...106 OM131 Chapter 5 P1939 OM 131 R11 Fig 5 9 SLS System Mk IV Gas Schematic Drawing P193940S1...
Page 123: ...OM131 111 P1939 OM 131 R11 Chapter 5 Fig 5 14 SLS System Mk IV Bottle Assembly...