Chapter 5 – Commissioning
5-1.8 Final System Check
Final check of the system involves checking the operation of the system, performing any necessary
adjustments and verifying that the system functions properly under normal operating conditions.
The following are the procedures for performing final system checkout:
1. Apply normal operating power to the entire system in accordance with the applicable
manufacturers instruction manuals.
2. Allow adequate time for the various units to stabilise. Unless specified otherwise in the
applicable instruction manuals, allow approximately one hour for the circuits to stabilise.
3. Carefully check each unit of the system for proper operation. If necessary, the Web Server may
be used in the Monitor tab to check proper operation within the controller.
4. Check manufacturers recommended adjustments and settings to ensure all units are set-up for
optimum function.
5. At the controller HMI (or in your Focus configuration), enter final operational preferences such as
schedules, passwords, flash watches, etc.
6. The system is ready for operation.
Summary of Contents for Omni C14
Page 1: ...Omni INSTALLATION INSTRUCTIONS...
Page 11: ...Omni INSTALLATION INSTRUCTIONS Preliminary Information 1...
Page 17: ...Omni INSTALLATION INSTRUCTIONS Mechanical Installation 2...
Page 31: ...Omni INSTALLATION INSTRUCTIONS Electrical Installation 3...
Page 53: ...Omni INSTALLATION INSTRUCTIONS Networking 4...
Page 74: ...Omni INSTALLATION INSTRUCTIONS Commissioning 5...