5-1.7.3 First Phase Testing
Perform the first phase of initial tests of the system as follows:
1. Turn off all electrical power to the Omni System.
2. Connect the controller to the computer by finding it on a connected network.
3. Turn on the computer and allow it to boot-up. Turn on the controller’s operating power. All
output circuits should be de-energised at this time.
4. Open a web browser and navigate to your controller's address and then login.
5. On the monitor tab, carefully adjust the controller’s input parameters, such as temperature,
pressure, switch position, etc. Adjust the values within normal and practical operating limits and
just enough to verify that a realistic change in output is produced. You may need to force the
block to achieve desired results. Click a block to see the block details and make adjustments.
6. When all inputs and outputs have been checked, return the input parameters to their original
settings. The first phase is completed.
5-1.7.4 Second Phase Testing
Perform the second phase of initial tests of the system as follows:
1. Turn on operating power to the primary output circuits such as pilot relays, motor controllers
and heat valves.
2. Ensure that operating power to plant machinery (compressors, fans, etc.) is turned off.
3. Open a web browser and navigate to your controller's address and then login.
4. On the monitor tab, carefully adjust the controller’s input parameters. Adjust the values within
normal and practical operating limits and just enough to verify operation of the primary output
circuits. You may need to force the block to achieve desired results. Click a block to see the block
details and make adjustments.
5. When all outputs have been checked for proper operation, return the input parameters to their
original settings. The second phase is completed.
5-1.7.5 Third Phase Testing
Perform the third phase of initial tests of the system as follows:
1. Turn on operating power to the plant machinery in accordance with the manufacturers
instruction manuals.
2. Open a web browser and navigate to your controller's address and then login.
3. On the monitor tab, carefully adjust the controller’s input parameters. Adjust the values within
normal and practical operating limits and just enough to verify control and operation of the
plant machinery. You may need to force the block to achieve desired results. Click a block to see
the block details and make adjustments.
4. When items of plant machinery have been checked for proper operation, return the input
parameters to their original settings. The third phase is completed.
5. Turn off operating power to the Omni controller.
6. Repeat procedures in 5-1.7.3 through 5-1.7.5 for the other controllers.
Summary of Contents for Omni C14
Page 1: ...Omni INSTALLATION INSTRUCTIONS...
Page 11: ...Omni INSTALLATION INSTRUCTIONS Preliminary Information 1...
Page 17: ...Omni INSTALLATION INSTRUCTIONS Mechanical Installation 2...
Page 31: ...Omni INSTALLATION INSTRUCTIONS Electrical Installation 3...
Page 53: ...Omni INSTALLATION INSTRUCTIONS Networking 4...
Page 74: ...Omni INSTALLATION INSTRUCTIONS Commissioning 5...