1.3 ATTACHMENTS.

Gas attachment (II

2H3+ 

category appliance).

Our boilers are designed to operate with methane 

gas (G20) and LPG. Supply pipes must be the 

same as or larger than the 1/2”G boiler fitting. 

Before connecting the gas line, carefully clean 

inside all the fuel feed system pipes to remove any 

residue that could impair boiler efficiency. Also 

make sure the gas corresponds to that for which 

the boiler is prepared (see boiler data-plate). 

If different, the appliance must be converted 

for operation with the other type of gas (see 

converting appliance for other gas types). The 

dynamic gas supply (methane or LPG) pressure 

must also be checked according to the type used 

in the boiler, as insufficient levels can reduce 

generator output and cause malfunctions.
Ensure correct gas cock connection. The gas 

supply pipe must be suitably dimensioned 

according to current regulations in order to 

guarantee correct gas flow to the boiler even 

in conditions of max. generator output and 

to guarantee appliance efficiency (technical 

specifications). The coupling system must 

conform to standards.

Combustible gas quality.

 The appliance has been 

designed to operate with gas free of impurities; 

otherwise it is advisable to fit special filters 

upstream from  the appliance to restore the 

purity of the gas.

Storage tanks (in case of supply from LPG 

depot).

- New LPG storage tanks may contain residual 

inert gases (nitrogen) that  degrade the mixture 

delivered to the appliance casing functioning 

anomalies.

- Due to the composition of the LPG mixture, 

layering of the mixture components may occur 

during the period of storage in the tanks. This 

can cause a variation in the heating power of 

the mixture delivered to the appliance, with 

subsequent change in its performance.

Hydraulic attachment.
Important:

 In order not to void the warranty  

before making the boiler connections, carefully 

clean the heating system (pipes, radiators, etc.) 

with special pickling or de-scaling products to 

remove any deposits that could compromise 

correct boiler operation.
Water connections must be made in a rational way 

using the couplings on the boiler template. The 

boiler safety valve outlet must be connected to a 

discharge funnel. Otherwise, the manufacturer 

declines any responsibility in case of flooding if 

the drain valve cuts in.

Important:

 to preserve the life and efficiency of the 

domestic hot water exchanger, it is recommended 

to install the “polyphosphate proportioner” kit in 

the presence of water whose characteristics can 

give rise to scale deposits (in particular, and as 

an example, the kit is recommended when water 

hardness is higher than 25 French degrees).

Electrical connection

. The “Zeus kW” boiler 

has an IPX4D protection rating for the entire 

appliance. Electrical safety of the unit is reached 

when it is correctly connected to an efficient 

earthing system as specified by current safety 

standards.

Important

: Immergas S.p.A. declines any 

responsibility for damage or physical injury 

caused by failure to connect the boiler to an 

efficient earth system or failure to comply with 

the reference standards.
Also ensure that the electrical installation 

corresponds to maximum absorbed power 

specifications as shown on the boiler data-plate. 

Boilers are supplied complete with an “X” type 

power cable without plug. The power supply 

cable must be connected to a 230V ±10% / 50Hz 

mains supply respecting L-N polarity and earth 

connection;  , this network must also have a 

multi-pole circuit breaker with class III over-

voltage category. When replacing the power 

supply cable, contact a qualified technician (e.g. 

the Immergas After-Sales Technical Assistance 

Service).

The power cable must be laid as shown. In the 

event of mains fuse replacement on the control 

card, use a 3.15A quick-blow fuse.

For the main power supply to the appliance, 

never use adapters, multiple sockets or extension 

leads.

Summary of Contents for ZEUS 24 Superior

Page 1: ...ZEUS 24 28 kW IE Instruction booklet and warning 1 038761ENG...

Page 2: ...ct correctly Maintenance must be carried out by skilled technical staff The Immergas Authorised After sales Service represents a guarantee of qualifications and professionalism The appliance must only...

Page 3: ...sure sufficient space for normal servicing therefore it is advisable to leave a clearance of at least 3 cm between the boiler casing and the vertical sides of the cabinet Leave adequate space above th...

Page 4: ...ranty before making the boiler connections carefully clean the heating system pipes radiators etc with special pickling or de scaling products to remove any deposits that could compromise correct boil...

Page 5: ...t function disabled i e it must be set to On Off mode The CRD cannot be used for plants divided into zones Electrical connection of the Remote Friend ControlV2 or chronothermostat On Off Optional The...

Page 6: ...s Cut the seal in the relative groove at the desired diameter 80 run it along the bend and fix it using the sheet steel plate Insert the exhaust pipe with the male end smooth into the female side of t...

Page 7: ...the boiler the fumes separator positioned on the air fumes extraction well must be adjusted Fig 1 12 Adjustment is carried out by loosening the front retainer screw and moving the indicator to the cor...

Page 8: ...Exhaust m 2 0 Terminal complete with concentric hori zontal intake exhaust 80 125 Intake and Exhaust 33 m 2 0 m 5 5 Intake m 14 3 Exhaust m 11 0 Terminal complete with concentric horizontal intake exh...

Page 9: ...t kits 80 125 Kit assembly Fig 1 18 install the bend with flange 2 on the central hole of theboiler inserting the seal 1 and tighten using the screws in the kit Fit the male end smooth of the adapter...

Page 10: ...flues and air intake pipes according to the diagram shown in the figure Fig 1 22 Fumes are expelled from duct S Air is taken in through duct A for combustion Intake duct A can be installed either on...

Page 11: ...red use 80 pipes with insulation see insulated separator kit 80 80 chapter Insulated separator kit 80 80 Kit assembly Fig 1 26 install flange 4 on the central hole of the boiler fitting seal 1 and tig...

Page 12: ...kit optional air intake takes place directly from the environment in which the boiler is installed and the fumes are expelled in an individual flue or directly to the outside The boiler in this config...

Page 13: ...tail to ensure maximum reliability Thelowerinspectionflangeensurespracticalcontrol oftheboilerandthecoiledheatexchangerandeasy internal cleaning The domestic water attachments are found on the flange...

Page 14: ...irculation pump 9 Gas valve 10 3 way valve motorised 11 System filler tap 12 System expansion tank 13 Domestic hot water probe 1 17 ZEUS 24 28 KW BOILER COMPONENTS 14 Stainless Steel Boiler 15 3 bar s...

Page 15: ...devices for flue extraction and relative accessories switch off the appliance and on completion of operations ensure that a qualified technician checks efficiency of the ducting or other devices Neve...

Page 16: ...it and that the system is free of air deaerated circulating pump blocked free the circulating pump If this phenomenon occurs frequently contact a qualified technician for assistance e g Immergas Techn...

Page 17: ...elow 4 C and stops once it exceeds 42 C The antifreeze function is guaranteed if the boiler is fully operative and not in block status and is electrically powered To avoid keeping the system switched...

Page 18: ...nd or exhaust terminals are not blocked check activation of the no air safety pressure switch ensure activation of all adjustment devices seal the gas flow rate regulation devices if settings are modi...

Page 19: ...ESHOOTING N B Maintenance must be carried out by a qualified technician e g Immergas Technical Assistance Service Smell of gas Caused by leakage from gas circuit pipelines Check sealing efficiency of...

Page 20: ...f gas by turning in a clockwise direction the heating potential increases and in an anti clockwise direction it decreases Adjust the boiler minimum thermal input Fig 3 3 N B only proceed after having...

Page 21: ...seconds LED 7 650 seconds Standard setting LED 8 Heating switch on delay request from Room thermostat and Remote Friend ControlV2 The boiler is set to switch on immediately after a request In the cas...

Page 22: ...n the casing Unhook the lower part of the casing as described in the figure Pull the casing 4 forwards and up at the same time see figure to detachit from the upper hooks 3 15 YEARLY APPLIANCE CHECK A...

Page 23: ...erted in the test pressure outlet of the modulating adjustable gas valve and on the sealed chamber positive pressure test outlet The power data given in the table is obtained with intake exhaust pipe...

Page 24: ...ppm 123 71 161 84 165 80 Flue temperature at nominal heat output C 108 109 107 Flue temperature at minimum heat output C 87 91 91 Zeus 28 kW Gas nozzle diameter mm 1 35 0 79 0 79 Supply pressure mbar...

Page 25: ...loss at case with burner On Off 0 40 0 89 0 60 0 62 Heat loss at flue with burner On Off 5 50 0 03 5 50 0 01 Heating circuit max working pressure bar 3 3 Heating circuit max working temperature C 90...

Page 26: ......

Page 27: ......

Page 28: ...mmergas com Immergas S p A 42041 Brescello RE Italy Tel 0522 689011 Fax 0522 680617 Certified company ISO 9001 This instruction booklet is made of ecological paper Cod 1 038761ENG rev ST 002107 000 10...

Reviews: