24
Response FF80
- Installation
27 MOUNTING THE BOILER
1.
The boiler may be prewired to the loose
electrical connector and secured with the
cable clamps. Refer to Frame 39.
2.
Lift the boiler onto the wall mounting frame,
locating it over the tabs at the top of the
frame.
3.
Lower the boiler into position.
4.
Remove plastic plugs and check that 'O'
rings are in place (spare 'O' rings in the
hardware pack).
5.
Fit the filter to the DHW inlet valve as
shown.
IMPORTANT.
This must not be omitted.
6.
Engage and tighten the 5 pipe unions.
7.
Fix the pressure relief valve drain pipe to the
pressure relief valve, using the nut and olive
supplied in the hardware pack.
28 CONNECTING THE TURRET TO THE BOILER
SIDE FLUE OUTLET
INSTALLATION
open ends of the turret clamp under the 2 studs and
fixing it in the middle with the single M5 x 10mm pozi-hex
screw provided.
1.
Mate the turret to the flue.
2.
Secure the flue turret on top of the boiler by inserting the
3.
Drill a 3.2mm hole through
the flue via the hole
already present in the
turret. Secure the turret
to the flue, using the
self tapping screw
provided.
4. Flues over 1 metre long.
Fix the flue support bracket
to the wall, using the wall
plug and wood screw.
•
For standard
installations use the
short wood screw.
•
If the 'stand-off' option
is used secure the
support bracket, using
the spacer bracket and
long wood screw.