5-4
Operator Guide
5. Close the rear door of the rack.
6. Plug all external device power cords into the electrical outlets.
7. Switch on power to all external devices attached to the rack (including rack expansion
drawers).
Note: Before setting the Power button to on, wait for the operator panel display to display
the word “Stand-By.”
8. Set the Power button to on (button pushed in).
Key Mode Switch
Normal
Secure
Service
Operator Panel
Power Button
9. If power does not come on, ensure that the power cord is plugged into a grounded
electrical outlet, and refer to “Appendix F. System Power States” for additional startup
and shut down procedures. If this does not solve the problem, refer to the
AIX Problem
Solving Guide and Reference manual.
When you press the Power button, the Power light comes on and the system starts
power-on self tests (POST). During the POST, numbers are displayed in the three-digit
display.
Summary of Contents for ThinkPad R30
Page 1: ...7015 Models R30 R40 and R50 CPU Enclosure Operator Guide...
Page 12: ...xii Operator Guide...
Page 16: ...xvi Operator Guide...
Page 20: ...1 4 Operator Guide...
Page 132: ...4 10 Operator Guide AC Rack Cables and the CPU Enclosure Connectors CPU Enclosure...
Page 156: ...6 4...
Page 194: ...10 4 Operator Guide...
Page 238: ...B 8 Operator Guide...
Page 248: ...D 4 Operator Guide...