UPS5000-E-(50 kVA-300 kVA)
User Manual (50 kVA Power Modules)
3 Installation
Issue 02 (2017-02-25)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
116
Figure 3-81
Installing connecting kits (UPS5000-E-200K-FM)
----End
3.3.2 Connecting Power Cables
Context
Cable connection for the UPS5000-E-200K-SM is used as an example. The parallel power
cables for different UPS models can be connected in a similar way.
Procedure
Step 1
Ground each UPS in a parallel system separately, and connect power cables and battery cables
according
Step 2
Based on the site configurations, select a parallel connection method to connect cables for the
parallel system.
shows a typical conceptual diagram for a 1+1 parallel system, and
shows the cable connections for this system.