Preparing the
Preparing the compute module
compute module for installation
for installation
Procedure
Procedure
1. Observe the following warnings:
WARNING:
WARNING: The front panel Power On/Standby button does not shut off system power.
Portions of the power supply and some internal circuitry remain active until AC power is
removed.
To reduce the risk of personal injury, electric shock, or damage to the equipment, remove
power from the compute module:
For rack and tower servers, remove the power cord.
For server blades and compute modules, remove the server blade or compute module
from the frame.
WARNING:
WARNING: To reduce the risk of personal injury from hot surfaces, allow the drives and the
internal system components to cool before touching them.
2. Update the system ROM.
Locate and download the latest ROM version from the Hewlett Packard Enterprise Support Center website
Hewlett Packard Enterprise Support Center website . Follow the instructions
on the website to update the system ROM.
3. Update the system ROM.
Locate and download the latest ROM version from the Hewlett Packard Enterprise Support Center website
(http://www.hpe.com/support/hpesc
http://www.hpe.com/support/hpesc). To update the system ROM, follow the instructions on the website.
4. Power down the compute module.
a. Shut down the OS as directed by the OS documentation.
b. To place the compute module in standby mode, press the Power On/Standby button. When the compute module enters standby
power mode, the system power LED changes to amber.
c. Disconnect the power cords (rack and tower servers).
5. Do one of the following:
Remove the compute module from the rack, if necessary.
Remove the compute module or compute module blade from the frame.
6. Place the compute module on a flat, level work surface.
7. Remove the access panel.
8. Remove any options or cables that may prevent access to the TPM connector.
9. Proceed to Installing the TPM board and cover .
Preparing the compute module for installation
95
Summary of Contents for Synergy 480 Gen10
Page 6: ...Component identification Component identification 6 ...
Page 10: ...Front panel LEDs and buttons 10 ...
Page 15: ...Smart Carrier NVMe SCN drive LED definitions 15 ...
Page 32: ...Operations Operations 32 ...
Page 45: ...Setup Setup 45 ...
Page 90: ...HPE Trusted Platform Module 2 0 Gen10 option HPE Trusted Platform Module 2 0 Gen10 option 90 ...
Page 94: ...Installing the Trusted Platform Module board Installing the Trusted Platform Module board 94 ...
Page 97: ...4 Proceed to Preparing the compute module for operation Installing the TPM board and cover 97 ...
Page 103: ...Cabling Cabling 103 ...
Page 105: ...Energy pack option cabling Energy pack option cabling 105 ...
Page 108: ...Electrostatic discharge Electrostatic discharge 108 ...
Page 111: ...Specifications Specifications 111 ...