12. Click the
Apply
button to save the changes.
Adding a Subnet Manager
Adding additional subnet managers (in addition to the one that is provided by default on the InfiniBand
system) should only be done by experienced users.
In the event that additional switch is added to an InfiniBand fabric, an additional subnet manager is
added by default (one is the master, and one is the standby).
In most instances, you should use the default subnet manager.
1. Open the Subnet Management window by selecting InfiniBand > Subnet Management.
Refer to
“Viewing the Subnet Manager Configurations” on page 62
.
2. Click the
Add
button.
The Add a Subnet Manager dialog box appears.
3. Enter a subnet prefix for the subnet manager in the
Subnet Prefix
field.
4. Enter a priority number for the subnet manager in the
Priority
field. The value is an integer
between 0 (the default) and 15.
The priority number tells the subnet manager how to interact with other subnet managers; the
highest priority (lowest number) subnet manager becomes the master.
5. Use the default subnet management key in the
smKey
field, which is 00:00:00:00:00:00:00:00.
The smkey is a 64-bit subnet management key that is assigned to the subnet manager.
Summary of Contents for 376227-B21 - ProLiant InfiniBand 4x Fabric Copper Switch
Page 10: ...viii ...
Page 20: ...8 ...
Page 44: ...32 ...
Page 50: ...38 ...
Page 56: ...44 ...
Page 72: ...60 ...
Page 92: ...80 ...
Page 104: ...92 ...
Page 116: ...104 ...
Page 122: ...110 ...
Page 130: ...118 ...