6.5 Operation and maintenance
6.5.1 Compressor start-up
The table below shows the required procedures and points before commissioning the
compressor.
Items
Check Points
Remarks
Leakage test
1. Inject 13.5 bar of nitrogen.
2. No leakage within 12 hours.
3. Mark the confirmed pressure on the pressure gauge.
1. Close the service valve on the
evaporator
Vacuum test
1. Vacuum pressure should below 750mmHg.
2. Maintain the vacuum state for 12 hours and confirm
whether the degree of vacuum has changed or not.
1. High pressure gauge must be
closed (no vacuum scale).
2. Do not conduct electrical testing
under vacuum state.
Lubricant oil
refilling
1.Use vacuum method and the angle valve on the
return flange of compressor for filling lubricant oil
2. Fill the oil until oil display at H scale. Verify the oil
level and refill (if necessary) after commissioning
3.Remove the wiring of the built-in oil pump to avoid
malfunction of the oil pump due to insufficient oil
which will result in damage to the oil pump
4.The oil heater should be powered on 24 ~ 48 hours
before compressor started to ensure oil temperature
is above "evaporation temperature " + 20
℃
"
1. The oil level should not be higher
than the H scale on the oil display
to avoid agitating the oil when the
gear rotates.
2. Determine the lubricating oil
heating time on condition like
under high latitude or cold area.
Refrigerant refilling
1. Confirm whether the chilling water pump and the
cooling water pump are running before refrigerant
filling.
2. Firstly add the gaseous refrigerant to above
saturation temperature 0
℃.
3. Fill the gaseous refrigerant to 2bar (g) after
connecting the oil pump power.
4. Then charge the liquid refrigerant to 80% of the
standard amount.
1. Record the amount of refrigerant
filled.
Motor fluid spray
volume
1. Adjust firstly the angle valve opening of the motor
housing to 2 cycles, and then open fully the outlet
valve at the bottom of the motor housing.
1. Please adjust the opening of the
valve according to the actual
maximum load condition of the
model and control the motor
temperature at <90
℃.
2. The present specifications are
Pt100 (or Pt1000) a total of 4
groups, need to be connected to
the control system to monitor
motor temperature.
Control setting
1. Verify if the electrical specifications of the Actuator
and hot gas bypass valve are correct.
2. Actuator: Control signal of 5% ~ 100% is 4.8 ~ 20mA
(or 0.5 ~ 10V), check if the actuator indicator
steering is rotating.
3. Actuator starting point is set to be 5% (for start-up
program).
4. Hot gas bypass valve: check if movement from 0% ~
100% is normal.
1. Make sure the Actuator is
working properly.