4. Locate the center of the bin and place the center well into position with the vertical shaft in the
gearbox at the center of the bin.
NOTE:
When placing the center well at the center of the bin, GSI recommends a tolerance of
+/-0.25 in. (both directions) for the slight adjustment of sweep length to enable the sweep to
run without any interference.
NOTE:
GSI does not recommend installing the Direct Gear Drive Power Sweep in concrete. When
flush-floor installations are necessary, a pre-formed trench is needed. A steel trench cover
adequate for the grain height and trench size must be installed. Consult the factory for
further information.
Figure 3-5
Center well placement
PNEG-2108
8" and 10" Standard Duty and IW Standard Duty
21