5. Installation
22
PNEG-1162CEX
DMC DIII Stir-Ator
Minimum Cable Requirements
1. Run a five (5) core cable, as shown
in Figure 5AF below, Figure 5AG on Page 23 and Figure 5AH
, from the slip ring junction box to the beam box, running through the openings given and
over the cable arms.
2. BEFORE CUTTING TO LENGTH, CHECK THERE IS SUFFICIENT LENGTH TO PREVENT
DAMAGE AS THE TROLLER MOVES UP AND DOWN THE BEAM.
3. CHECK THAT THE LOOP OF CABLE DOES NOT FOUL ON ANY PARTS OF THE STIRRER.
Figure 5AF Cable Route in Centre Yoke
Main Current
Protection
Supply to
Slip Ring *
Slip Ring to
Beam Box
Beam Box to
Auger Motor
Beam Box to
Track Motor
Twin Auger,
3 Phase
Fuse
3 x 25A
6 mm²
6 Core H07
4 mm²
5 Core H07
1.5 mm²
4 Core H07
1.5 mm²
3 Core H07
Triple Auger,
3 Phase
Fuse 3 x 3
3 x 32A
6 mm²
6 Core H07
6 mm²
5 Core H07
1.5 mm²
4 Core H07
1.5 mm²
3 Core H07
Twin Auger,
1 Phase
Fuse
2 x 25A
6 mm²
6 Core H07
6 mm²
5 Core H07
2.5 mm²
3 Core H07
1.5 mm²
3 Core H07
Triple Auger,
1 Phase
Motor Protection
Unit 32A
6 mm²
6 Core H07
6 mm²
5 Core H07
2.5 mm²
3 Core H07
1.5 mm²
3 Core H07
* Note, sixth core carries 230 VAC signal for ‘Stir Guard’.
5 Core H07 cable