Assembling the Temperature Cable Bracket
The temperature cable brackets are installed to the roof rafters and support the temperature cables.
Before You Begin
Determine the correct location of the temperature cable brackets within the structure of the A-frame
Assembly. See
About Temperature Cable Brackets and A-Frame Assemblies, page 96
.
What You Should Know
The A-frame assembly consists of two roof rafters, purlin clips, purlins and possibly X-bracing. The tem-
perature cable brackets should be installed when the A-frames are assembled.
There are two different temperature cable brackets used (CTR-0013 and CTR-0973). For purlin location
2, use temperature cable bracket (CTR-0973) with four hole connection to the rafter. For purlin location 4,
use temperature cable bracket (CTR-0013) with three hole rafter connection.
NOTE:
The temperature cable bracket must be installed at specific locations, see
Cable Brackets and A-Frame Assemblies, page 96
1. Attach a right purlin clip (C), a left purlin clip (D) and a temperature cable bracket (B) to the roof
rafter (A) and install two flange bolts (E) and two flange nuts (F).
NOTE:
If no X-bracing is installed, install three flange bolts (E) and three flange nuts (F).
2. After all purlins and X-bracing are installed in the A-frame, tighten all hardware to the recommended
torque specifications. See
Bolt Torque Specifications, page 28
.
PNEG-4472
72 Ft Diameter Z-Tek Bins
99
Summary of Contents for 40-SERIES
Page 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...