Guidelines for Installing a Sidedraw System
A sidedraw system will allow content unloading using gravity, and is done from the side of the bin.
General Guidelines to Follow Before Installing A Sidedraw System:
NOTE:
If a sidedraw system is installed, the standard 3/4 in. anchor bolts must be replaced with 1 in.
anchor bolts.
• Side discharge is only permitted in stiffened bins when a GSI manufactured sidedraw flume system
has been installed. No corrugated steel bin must be unloaded through the side wall without installa-
tion of such a system and permission of the manufacturer.
• A sidedraw should not be the only discharge system available. A standard center discharge and
conveyor must be installed.
• Installation of multiple systems may require additional wind rings and must be placed a minimum of
90 degrees apart. Installation of multiple systems requires approval of GSI.
• Sidedraw systems are intended for use with dry, flowable grain. Sidedraws are not to be used for
poorly flowing products. This is not unique to GSI bins and flume systems, but is a general rule for
such systems.
• In multiple system installations, only one sidedraw may be used at any one time.
• Filling must not be occurring at the same time as grain is being withdrawn through the sidedraw
flume system.
• Prolonged storage of grain in the sloped condition produced by sidedraw discharge may accelerate
differential settlement and result in deformations of the bin. After using the sidedraw system, the
sloped grain must be returned to a near level condition by use of the center discharge. Leveling of
the grain should also allow more even consolidation of foundation and fill soils and produce more
even settlement of the bin.
• If past experience or geotechnical investigations indicate significant foundation level soil variations
or a site propensity toward differential settlement, sidedraw usage may be prohibited or severely
restricted. In this situation the use of a flume system should be reviewed with geotechnical consul-
tants or the foundation engineer.
• Before installing, determine if bin design is a two post stiffener (A).
• Do not install a discharge chute on a vertical seam.
• A discharge chute should be installed at the standard height (C).
158
PNEG-4472
72 Ft Diameter Z-Tek Bins
Summary of Contents for 40-SERIES
Page 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...