Center Collar Placement
The following figure gives the approximate height needed to install the center collar.
With one sidewall ring in place, position the center collar at the height specified, measuring from the
bottom of the center collar to the foundation as shown. If additional rings are required for construction pur-
poses, add 44 in. for each additional ring.
NOTE:
It is better to set the center collar a little too high. Do not set the center collar too low.
Figure 8-17
Center collar placement
A
251 in. (20 ft - 9 in.) (637.54 cm) from foundation to bottom of center collar on 72 ft diameter bin
NOTE:
Make sure the center pole is adjustable up and down.
PNEG-4472
72 Ft Diameter Z-Tek Bins
113
Summary of Contents for 40-SERIES
Page 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...