7.
Place waste containers below the ratio check noz-
zles and start a ratio check dispense. Adjust the
ratio check opening screws until the pressures dis-
played are near the values previously recorded
when dispensing through the mixer (step 4).
8.
Press
to enter the Setup screens then press
left or right to navigate to
screen. Turn
on the “Enable Ratio Check Weight Mode Entry”
option.
9.
Press
to exit the setup screen and verify the
ratio check option is selected.
10. With new waste containers below the ratio check
nozzles, start the dispense by pressing the foot-
switch or
. At the end of the dispense, enter the
A (Red) and B (Blue) material weights into the
prompt boxes. Enter the weight of each bucket for
both materials.
NOTE:
After entering the net weight of B (Blue) material,
the ADM will inform the user how close the respective
flow of the pump was to the desire rate.
11. Press
to accept the information.
NOTE:
The ADM will respond by generating a “System
Learning Setpoint” advisory and the corresponding advi-
sory light will be illuminated on the machine light tower
(if installed).
12. Press
to accept the advisory. Repeat steps 10
through 11 until the percentages approach zero and
the advisory is removed.
NOTE:
The machine will be calibrated for the flow and
ratio selected once the advisory is removed.
13. If the user needs to operate at a second flow or
ratio, repeat the calibration process for the second
desired flow or ratio.
NOTE:
The machine will store the necessary control
data for both calibration points.