5. Operation
5. Operation
3. Backup Mode Logic
(Keep the Battery at a certain SOC and only use it during power outage):
Backup SOC Setting Range: From Battery “Overdischarge SOC” to 100%
PV Power Using Priority: Battery>Load>Grid
Load Support Priority: PV>Grid>Battery
Battery Charging Power comes from PV.
(If “Charging from Grid” is allowed, it can also come from Grid)
*The “Backup Mode” is not applicable for Lead-acid batteries.
Settings
Backup
2015-02-23 19 35
Figure 5.38 Backup Mode
ON
OFF
Y E S
=
< E N T >
N O
=
< E S C >
NOTE:
Unless specially required, it is suggested to keep the "Charging from Grid"
as "Allow". If it is set to "Not Allow", the battery force charging logic will be
affected and may lead to a fully discharged battery.
4. Off-Grid Mode Logic (For Off-grid use and AC-Grid Port Disconnected):
OverDischg SOC for Off-Grid Setting Range: From Battery “Forcecharge SOC” to 100%
PV Power Using Priority: Load>Battery
Load Support Priority: PV>Battery
Battery Charging Power comes from PV.
Settings
Off grid
2015-02-23 19 35
Figure 5.39 Off grid Mode
ON
OFF
Y E S
=
< E N T >
N O
=
< E S C >
5.6.5.3 Battery Wakeup
Figure 5.40 Battery Wakeup
.
This function should be activated only after the installation
In the case of a low battery
voltage shutdown, the inverter will shut-down. This setting can be enabled, so when the
inverter detects PV or grid it wakes up the battery.
This function conflicts with the battery
reverse polarity protection( If the installer connects cables with wrong polarity the inverter
,
can protect itself from damage).To avoid the possible damage during installation do not
,
activate battery wakeup function before finishing the first commissioning.
Settings
Srorage Energy Set
2015-02-23 19 35
Meter Select
Storage Mode Select
Y E S
=
< E N T >
N O
=
< E S C >
Battery Wakeup
.42.
.43.