31
SECTION 4 - INSTALLATION
4
MDE-5224F
Completing Installation
To complete the installation, inspect all the connections and cable routing before applying power.
For start-up information, refer to
MDE-5221 FlexPay IV CRIND Start-up
Manual.
IMPORTANT INFORMATION
For detailed block diagrams of cable connections, refer to
Registering Kits with Gilbarco Warranty
To register the kits with Gilbarco Warranty:
1
After the kits are successfully installed, register kits through web commissioning within 30 days.
2
Provide the correct model and serial numbers.
Note: Registering the kits ensures that proper warranty is applied.
The Advantage Retrofit Kit part number is EPK M7 ADV.
Cable routing is critical. It is very important to route and dress the cables
properly. Exercise care in routing the cables, keeping in mind that the door(s)
opens and closes for service. The cables must be dressed neatly. Ensure that
there is no interference after the cables are connected and routed.
ESD ground straps can be bundled together, but need to be separated from
data and power cables.
IMPORTANT INFORMATION