____________________________________________Appendix F – Startup, Inspection and Tests, Page F-1
Pre Start-Up Check
Overview
As one of the benefits of purchasing a Gaylord ClearAir Unit is a complete Start-Up Inspection is performed
by a Gaylord Authorized Representative or a Gaylord Certified Service Agency. These tests must be
conducted prior to use by the operator. Typically at the time the Start-Up Inspection is performed, the
operation and general maintenance of the Gaylord equipment is demonstrated and described to the
operating personnel. It is the responsibility of the Gaylord Authorized Representative or Agency to
coordinate the date of Start-Up with any personnel such as the GC, owner, owner’s rep, Fire Marshall, fire
protection contractor, air balancer etc., required to witness the Start-Up.
Pre Start-Up Requirements
Before a Gaylord Start-Up can be performed, the responsible contractor or dealer must have the ClearAir
Unit installed and operating. The following is a check list of items that must be completed prior to a Start-
Up being conducted.
Pre Start-Up Check List
____ ClearAir Unit is installed as per Gaylord Submittal Drawings.
____ Check to ensure that duct work is a minimum 16 GA steel or 18 GA stainless steel, all welded and
continuously welded to the connection at the ClearAir Unit.
____ If the unit was shipped in sections, check for proper assembly of the unit as shown on pages B-1 and
B-2.
____ Check the fan section to ensure that the shipping straps have been removed and the fan isolators
have been unscrewed as per the instructions on page 6-1.
____ Check to see that all required electrical and plumbing connections between the Gaylord Command
Center, Wash Control Cabinets and the ClearAir Unit are completed per plans and operational.
____ Check to see that all pre-filters and ESP Cells are installed.
____ If a media bed odor control system was provided, make sure that it was installed per the instructions
on page B-1.
____ If a spray odor control system was provided, locate the 5 gallon pail of GS-710 provided in the spray
odor control cabinet. Remove the lid and install the pickup tube and level sensor.
____ Start exhaust fan and check for proper fan rotation. Warning: A fan running backwards will
overheat the motor and can cause bearing failure or other serious damage and will void the
Warranty.