EN
23
Installation Instructions
Commissioning:
• Connect central energy meter to GLB Modbus terminal “E-Meter” (refer to Mainboard simplified
connection diagram) Note, Modbus connection between energy meter and GLB must be
connected as following: A- (energy meter) to A- (GLB “E-meter” terminal) and B+ (energy meter) to
B+ (GLB “E-meter” terminal)
• Connect Data Link to GLB Modbus terminal “Data Link” (refer to Mainboard simplified connection
diagram) Note, Modbus connection between GLB Wallboxes must be connected as following: A-
to A- and B+ to B+ see (figure 18) (figure 19).
• Config SW1 (DIP 5-6) see (figure 17) (figure 18) (figure 19).
• Config energy meter in distribution box to Modbus address no.100 (9600 baud, no parity, one
stop bit).
• Config max current or max power (refer Dynamic Load Management (DLM) setting inthe web
interface).
It should be noted that SW1 (DIP 1–3) does not have a function for group load balancing. Instead,
group balancing is performed in the GLB Master’s web interface (see section entitled Load balancing
settings in the web interface).
When connections lost eg. master loose connection from energy meter or
master stops working, the slaves reduces the charging current to 6A. This state is indicated by a short
sound signal and a short yellow led signal every 60
seconds.
All load balancing settings in groups are carried out via the wallbox’s web interface.
To connect a mobile phone, tablet or computer to the wallbox, see the section entitled
Connecting to the wallbox´s Wi-Fi access point (AP).
The DLM meter connected – Group configuration’ option can be found under Settings.
The Fuse rating contract can be set (A), as can the value of the power rating contract
(kW), where relevant.
Dynamic Load Management (DLM) settings in the web interface