Hardware Installation
Installing/Removing the Server into/from the Rack
–
The operability of the safety mechanisms at the server e.g. stoppers or
holding back systems must be guaranteed.
–
The form of the rack support uprights must ensure the frontal screwing on of
the rails.
–
There is no support for the cable management delivered with the mounting
kit.
–
Frontally bolted telescopic rails or sliding rails.
The rails are provided with a linear alignment possibility to ensure also an
adjustment to different rack depths.
–
Climatic conditions.
For the ventilation of the installed server a large extent unhindered air intake
in the rack front and air discharge in the rear cover of the rack are necessary.
In principle, the ventilation concept plans that the necessary cooling is
reached by the horizontal self-ventilation of the installed devices (air flow
from the front to the rear).
–
Power supply.
For the installation in 3rd-Party Racks it is to be made certain that appro-
priate socket strips are present.
D
area for cable routing (cable area depth) and ventilation
E
area for front panel and ventilation
F
right and left area for support systems
P
PRIMERGY installation depth
a1
front left support upright
a2
front right support upright
b1
rear left support upright
b2
rear right support upright