Installation Instructions
26.1.11
Panda_4000s_PMS_SCB_FCB_eng.R04 - Kapitel/Chapter 5: Installation Instructions Seite/Page 73
Fig. 5.3.4-2: Installation example over the waterline FC version
5.3.5 Installation below waterline
If the generator can not be attached at least 600mm over the waterline, a vent valve must be installed into the raw
water line. Possible heeling must be taken into consideration if installed at the „mid-ship line“! This hose is split in the
middle and extended respectively at each end by an additional hose and a connecting pipe. Both hose ends must be
led out outside of the sound cover to one point, if possible 600mm over the waterline in the mid-ship line. The valve
is connected at the highest place to the two hose ends.
If the valve is jammed, then the cooling water line cannot be ventilated after the generator has been stopped, the
water column is not interrupted and water can enter the combustion compartment of the motor. This can quickly
cause damage to the motor!
1.
Raw water impeller pump
2.
Freshwater pump
3.
Water-cooled exhaust elbow
4.
Cooling water connection block
5.
Heat exchanger
6.
Raw water filter
7.
Water cock
8.
Raw water inlet
9.
Expansion tank
10. Vent valve
11. Oil cooler
12. Reducer