FAST & FLUID MANAGEMENT srl
A Unit of Idex Corporation
6
8. INSTALLATION REQUIREMENTS
SO300 has to be placed on a level and stable ground. Please install the machine by proceeding as follows:
à
230-240 VOLTAGE: power supply with a magneto-thermal protection device that intervenes when current
absorbed exceeds 16 Amps or for leakage current of 30 mAmps, according to local regulations.
à
115 VOLTAGE: power supply with a magneto-thermal protection device that intervenes when current
absorbed exceeds 25 Amps or for leakage current of 30 mAmps, according to local regulations.
Environmental conditions must be within the following limits:
Air temperature
10 to 40 °C
Relative humidity
30 to 90 %
During the installation it is advisable to use protective gloves to avoid injuries.
Connect the power cable to the
SO300 so that you can open
the door
Pull the cords fixed to the
wooden blocks
Before trying to start the
machine, make sure the screws
and the wooden blocks have
been removed from the
machine itself
Undo the feet of the machine, till the machine
wheels no longer touch the ground
Block the feet by doing their
respective lock nuts
SO300 shaker must not be installed in an working area classified as EX
Remove the bolts that fixe the machine to the pallet
Remove the screws at the inside of
the side panels
Set the machine level by
using an appropriate tool