Complete these steps:
1. Verify that tank stands are level and in the correct positions for system assembly. Top of top ring of each stand must be approximately 25" above floor.
Do
not elevate stands above floor level.
For best results, tank stand heights should be identical when possible. See diagram below.
2. Carefully set each 15 gallon tank in a tank stand and ensure tank is level and seated in stand. See Top View diagram to align tanks.
3. Measure and mark
center of
lower bulkhead hole
for
radial flow clarifier tank.
See diagram. Drill hole using 3" hole saw. Hole position aligns with side
hole in large tank.
See diagram in Section 1 for clarification
.
4. Using diagram below, mark upper hole locations on each tank. See diagram. Hole locations will be immediately across from each other when marked
properly. These holes are directly opposite lower side hole in radial flow clarifier tank.
5. Take a drill and a 3" hole saw bit and drill one hole in each tank.
6. Prepare/clean all holes for bulkhead installation as previously described.
Prepare Tanks & Install Fittings
5c
DRILL HOLES FOR BULKHEAD INSTALLATION (SMALL TANKS)
20"
Approx.
25" above
finished floor.
27-1/2"
Finished Floor
Step 3: Center
of Lower Hole
Step 1: Top of Upper Ring
Step 4:
Center of
Upper Holes
Radial Flow
Clarifier Tank
Mineralization
Tank
Align holes
with center
of tanks.
Top View
ATTENTION:
Review diagrams on next
page to better understand hole positions
and overall plumbing layout.