36
36
111628W
Revision date: 09.25.18
2. After attaching all pipe hangers to the frame, take the 112310 3/4"
pvc supply manifold and position it against the installed hangers.
NOTE:
This procedure shows attaching the manifold to the frame
before adding the supply tube assemblies. These tube assemblies
can be installed before you secure the manifold to the frame. Steps
3 and 4 describe the installation of the supply tubes.
INSTALL THE SUPPLY MANIFOLD — continued
4
Assembly Instructions
ATTENTION:
Handle the supply manifold carefully during installation to prevent damage
to the supply tube fittings! These can break if handled improperly! Actual fodder system
differs from what is shown in the photo below. Manifold installation is the same however.
Supply Manifold
STAND-ALONE UNIT
ONLY—
If you are attaching
the main water line at the
bottom, slide manifold up
during installation to provide
the needed clearance, or trim
to length as needed. Trim the
top of the manifold if desired
and cement the WF2990 slip
cap in place using pvc primer
and cement. See Page 3.
CONNECTING MULTIPLE SYSTEMS—
See the information on Page 4 if attaching the
water supply line to multiple fodder systems.
If the water main is attached to
the top of the manifold, install
the WF3311 ball valve at the
bottom. See Page 4.