Site Preparation
•
Install equipment into the lower half of the rack first to avoid making the rack top-heavy.
•
The rack should support approximately 600 pounds (272 kilograms).
Protective Grounding for the Rack
Use a rack grounding kit and a ground conductor that is carried back to earth or to another suitable
building ground.
All Extreme Networks switches are designed with mounting brackets that provide solid metal-to-metal
connection to the rack. If you do not use equipment racks, you can attach wiring terminals directly to
the mounting brackets for appropriate grounding. Alpine products have grounding terminals that are
mounted on the back of the chassis.
At minimum, follow these guidelines:
•
Ground equipment racks to earth ground.
—
CAD weld appropriate wire terminals to building I-beams or earth ground rods.
—
Use #4 copper wire.
—
Drill and tap wire terminals to equipment racks.
—
Position the earth ground as close to the equipment rack as possible to maintain the shortest
wiring distance possible.
—
Properly test the quality of the earth ground.
NOTE
Because building codes vary worldwide, Extreme Networks strongly recommends that you consult an
electrical contractor to ensure proper equipment grounding is in place for your specific installation.
•
Ground DC power supplies to earth ground by using the grounding terminals provided.
Space Requirements for the Rack
Provide enough space in front of and behind the switch so that you can service it easily. Allow a
minimum of 48 inches (122 cm) in front of the rack and 24 inches (61 cm) behind the rack. When using a
relay rack, provide a minimum of 24 inches (61 cm) of space behind the mounted equipment. Extra
room on each side is optional.
NOTE
Install your equipment rack near an easily accessible power outlet. When you need to disconnect the
power cable from your switch, remove it first from the power source and then from the switch.
Securing the Rack
The rack should be attached to the wiring closet floor with 3/8 inch (9.5 mm) lag screws or equivalent
hardware. The floor under the rack should be level within 3/16 inch
(5 mm). Use a floor-leveling cement compound if necessary or bolt the racks to the floor as shown in
Figure 11.
Summary of Contents for Alpine 3802
Page 17: ...Part 1 Common Features ...
Page 18: ......
Page 32: ...32 Extreme Networks Consolidated Hardware Guide Summary of Common Switch Features ...
Page 33: ...Part 2 Site Planning ...
Page 34: ......
Page 56: ...56 Extreme Networks Consolidated Hardware Guide Site Preparation ...
Page 57: ...Part 3 Summit Switch ...
Page 58: ......
Page 104: ...104 Extreme Networks Consolidated Hardware Guide Summit Switch Models ...
Page 114: ...114 Extreme Networks Consolidated Hardware Guide Summit Switch Installation ...
Page 115: ...Part 4 Alpine Switch ...
Page 116: ......
Page 122: ...122 Extreme Networks Consolidated Hardware Guide Alpine 3800 Series Switch Overview ...
Page 152: ...152 Extreme Networks Consolidated Hardware Guide Alpine 3800 Series Switch Power Supplies ...
Page 158: ...158 Extreme Networks Consolidated Hardware Guide Alpine 3800 Series Switch Management Module ...
Page 188: ...188 Extreme Networks Consolidated Hardware Guide Alpine 3800 Series I O Modules ...
Page 194: ...194 Extreme Networks Consolidated Hardware Guide Alpine 3800 Series Switch Fan Tray ...
Page 195: ...Part 5 BlackDiamond Switch ...
Page 196: ......
Page 202: ...202 Extreme Networks Consolidated Hardware Guide BlackDiamond 6800 Series Switch Overview ...
Page 218: ...218 Extreme Networks Consolidated Hardware Guide BlackDiamond 6800 Series Switch Chassis ...
Page 282: ...282 Extreme Networks Consolidated Hardware Guide BlackDiamond 6800 Series I O Modules ...
Page 290: ...290 Extreme Networks Consolidated Hardware Guide BlackDiamond 6800 Series Switch Fan Tray ...
Page 291: ...Part 6 Switch Operation ...
Page 292: ......
Page 296: ...296 Extreme Networks Consolidated Hardware Guide Initial Switch and Management Access ...
Page 297: ...Part 7 Appendixes ...
Page 298: ......
Page 340: ...340 Extreme Networks Consolidated Hardware Guide Module Technical Specifications ...