Installation
External ash removal
61
Check the height
Check the height of the connection flange with the
height of the ash bin used.
Fig. 9-101: Check the height
Slide the ash bin under the ejector and place the
connection flange on the ash bin. Adjust the
height with the support stand, so the connection flange
rests fully on the ash bin. The impact protection mat
and the chain must still be loose in this position.
Fig. 9-102: Check height with ash bin
If the correct height is set, fasten the support stand to
the floor with suitable screws.
Fig. 9-103: Support stand
Tighten the screws of the universal joint alternately and
evenly.
Fig. 9-104: Universal joint
Mount the position switch
Mount the position switch on the connection flange.
Initially only hand-tighten the screws.
Fig. 9-105: Position switch